Displaying 51 - 100 of 15570
CaseID![]() |
Title | Case Type | Status | DecisionStatus | ApplicationDate | DecisionDate | CaseOfficers | Heritage Authority |
---|---|---|---|---|---|---|---|---|
20647 | Proposed development and demolition of structures at 170 Roland Chapman Drive, Montclair, Durban | Permits | SUBMITTED | Letter | 2023-02-07 20:53:00 | 2023-03-15 11:15:00 | Nokubonga Dlamini, Khanyi Zondi | Amafa |
20646 | Hendrina South Grid Connection including a 132kV Powerline | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-02-07 17:20:00 | 2023-03-10 16:00:00 | Natasha Higgitt | SAHRA, MPHRA |
20644 | MOOKODI INTEGRATION PHASE 2: 132KV POWER LINES NEAR VRYBURG, NORTH WEST PROVINCE DEA Ref No: 14/12/16/3/3/1/678 | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2023-02-07 15:38:00 | 2023-03-16 11:30:00 | Sityhilelo Ngcatsha | SAHRA, NWPHRA |
20640 | Palm Ridge X43, Gauteng Province | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-02-07 08:35:00 | 2023-03-01 10:30:00 | Andrew Salomon | SAHRA, PHRA-G |
20638 | BOJANALA SPECIAL ECONOMIC ZONE (SEZ) | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-02-06 15:15:00 | 2023-03-17 06:15:00 | Sityhilelo Ngcatsha | SAHRA, NWPHRA |
20637 | Minor Works to 37 Kelvin Place | Permits | Closed (Approved) | Final Decision | 2023-02-06 13:47:00 | 2023-02-14 08:45:00 | John Pakwe, Khanyi Zondi | Amafa |
20627 | Proposed 132 kV transmission line between the Camel Thorn Solar Facility and Prieska Power Reserve’s industrial complex | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-02-06 10:51:00 | 2023-03-08 18:30:00 | Natasha Higgitt | SAHRA, NBKB |
20621 | 132 KV GRID CONNECTION TRANSMISSION LINE BETWEEN THE ORANGE RIVER SOLAR FACILITY 1 AND ESKOM’S HIGH VOLTAGE GROBLERSHOOP | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-02-06 08:43:00 | 2023-03-08 18:30:00 | Natasha Higgitt | SAHRA, NBKB |
20607 | Komati Power Station Solar PV and BESS facility | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2023-02-02 08:46:00 | 2023-03-10 16:00:00 | Natasha Higgitt | SAHRA, MPHRA |
20603 | Ama Superco 20 CC - Proposed Light Industrial Development located on the Remainder of Lot 20 Marburg No 5096 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Decision | 2023-02-01 15:05:00 | 2023-02-08 09:15:00 | Philani Ndabezitha, Khanyi Zondi, Ros Devereux | Amafa |
20598 | Proposed and Unauthorised Additions and Alterations to 18 Lilian Ngoyi Road, Windemere, Berea, | Permits | Closed (Approved) | Interim Comment | 2023-02-01 12:32:00 | 2023-02-08 10:45:00 | Philani Ndabezitha, Ros Devereux, Khanyi Zondi | Amafa |
20598 | Proposed and Unauthorised Additions and Alterations to 18 Lilian Ngoyi Road, Windemere, Berea, | Permits | Closed (Approved) | Final Decision | 2023-02-01 12:32:00 | 2023-03-01 15:00:00 | Philani Ndabezitha, Ros Devereux, Khanyi Zondi | Amafa |
20595 | MAPPING AND RESCUE EXCAVATIONS OF A LATE IRON AGE STONE WALL ON PORTION 191 OF THE FARM TWEEFONTEIN 915LS WITHIN POLOKWANE MUNICIPALITY, | Permits | Studies Pending | Letter | 2023-01-31 11:07:00 | 2023-03-30 09:30:00 | Sityhilelo Ngcatsha | SAHRA |
20594 | Springhaas to Artemis Grid Connection Line 2 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Decision | 2023-01-31 10:56:00 | 2023-03-17 11:45:00 | Sityhilelo Ngcatsha | SAHRA, HFS |
20592 | Springhaas to Artemis Grid Connection Line 1 | Section 38 (8) - Statutory Comment Required | Decision Passed | Final Decision | 2023-01-31 10:32:00 | 2023-03-13 03:00:00 | Sityhilelo Ngcatsha | SAHRA, HFS |
20591 | Isandlwana Rural Housing | Development | Studies Pending | Interim Comment | 2023-01-31 09:34:00 | 2023-02-08 10:00:00 | John Pakwe, Khanyi Zondi | Amafa, SAHRA |
20585 | Mining Right Application on Farm Middel Post 60, Kakamas | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2023-01-30 12:07:00 | 2023-02-28 08:45:00 | Natasha Higgitt | SAHRA, NBKB |
20581 | Birdsong Mast, Limpopo Province | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-30 11:34:00 | 2023-03-13 16:00:00 | Nokukhanya Khumalo | SAHRA, LIHRA |
20577 | Unauthorised Additions and Alterations to 62 Highlands Road | Permits | Closed (Approved) | Final Decision | 2023-01-28 10:12:00 | 2023-02-08 15:00:00 | Philani Ndabezitha, Khanyi Zondi, Ros Devereux | Amafa |
20576 | As Built Plans for 22 Inwabi Road | Permits | Closed (Approved) | Final Decision | 2023-01-27 16:41:00 | 2023-03-01 08:15:00 | John Pakwe, Khanyi Zondi, Ros Devereux | Amafa |
20576 | As Built Plans for 22 Inwabi Road | Permits | Closed (Approved) | Letter | 2023-01-27 16:41:00 | 2023-02-08 11:30:00 | John Pakwe, Khanyi Zondi, Ros Devereux | Amafa |
20573 | The Proposed Development of the Umlaas junction Light Industrial Estate on a 139-ha portion of the Remainder of Farm Crookes 15723, Mkhambathini Local Municipality, KwaZulu-Natal | Section 38 (8) - Statutory Comment Required | SUBMITTED | Final Comment | 2023-01-27 15:47:00 | 2023-02-09 13:45:00 | Sandisiwe Matole | Amafa |
20570 | Additions and Alterations to 554 Marine Drive | Permits | SUBMITTED | Interim Comment | 2023-01-27 11:02:00 | 2023-02-08 10:45:00 | John Pakwe, Khanyi Zondi, Ros Devereux | Amafa |
20565 | Khuba Secondary School, Nkandla Local Municipality | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-26 14:35:00 | 2023-03-01 12:30:00 | Nokubonga Dlamini, Khanyi Zondi | Amafa |
20564 | Proposed Establishment of a Hazardous Materials Storage Area, Keystone Park, Hammarsdale, KZN | Section 38 (8) - Statutory Comment Required | On Agenda | Final Comment | 2023-01-26 14:13:00 | 2023-02-10 16:15:00 | Celeste Rossouw, Khanyi Zondi | Amafa |
20560 | Alterations to house on 260 Innes Road and addition of a study loft for 15 year old triplets. | Permits | SUBMITTED | Letter | 2023-01-25 10:39:00 | 2023-03-15 13:15:00 | Sphephelo Dube, Khanyi Zondi | Amafa |
20559 | Bhobhonono housing project, Msunduzi Local Municipality | Section 38 (8) - Statutory Comment Required | Pending & Under Assessment | Interim Comment | 2023-01-25 09:26:00 | 2023-02-01 13:00:00 | John Pakwe, Khanyi Zondi | Amafa |
20558 | 69 St Andrews Drive | Permits | Closed (Approved) | Final Decision | 2023-01-25 01:30:00 | 2023-02-01 14:00:00 | Sphephelo Dube, Khanyi Zondi | Amafa |
20557 | Agricultural development on the farm Scherp Arabie, Marble Hall | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-24 17:12:00 | 2023-03-13 22:00:00 | Nokukhanya Khumalo | SAHRA, LIHRA |
20555 | Amendment Authorisation issued for Boschrand Photovoltaic (PV) 2 Solar Energy Facility near Dealesville, in the Free State Province. | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-24 16:13:00 | 2023-02-10 15:00:00 | Sityhilelo Ngcatsha | SAHRA, HFS |
20553 | Amendment Authorisation issued for Irene Photovoltaic (PV) Solar Energy Facility near Dealesville, in the Free State Province. | Section 38 (8) - Statutory Comment Required | Studies Pending | Letter | 2023-01-24 15:43:00 | 2023-02-13 10:30:00 | Sityhilelo Ngcatsha | SAHRA, HFS |
20552 | Proposed development of Claire PV 3 in Clayville, Gauteng | Section 38 (1) - Decision from Heritage Authority required | Closed (Approved) | Final Comment | 2023-01-24 15:01:00 | 2023-03-01 10:30:00 | Andrew Salomon | SAHRA, PHRA-G |
20550 | Part 1 EA Amendment Application for The Extension of the validity period for Environmental Authorisation (12/12/20/2321/2/1); Loeriesfontein 3 PV SEF | Section 38 (8) - Statutory Comment Required | For Noting | Final Comment | 2023-01-24 12:20:00 | 2023-03-10 16:00:00 | Natasha Higgitt | SAHRA, NBKB |
20548 | Part 1 EA Amendment Application for the Extension of the validity period for EA(12/12/20/2321/2/2); 132kv Grid Alignment and 132kv Eskom Portion of the shared On-Site Substation for the 100 MW Loeriesfontein PV SEF | Section 38 (8) - Statutory Comment Required | For Noting | Final Comment | 2023-01-24 11:45:00 | 2023-03-10 16:00:00 | Natasha Higgitt | SAHRA, NBKB |
20547 | Unauthrised Additions and Alterations to 202 Gordon Road, Windemere, Berea | Rectification | Pending & Under Assessment | Interim Comment | 2023-01-24 10:27:00 | 2023-02-01 14:15:00 | Philani Ndabezitha, Khanyi Zondi | Amafa |
20546 | Zandspruit Sewer | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-24 09:05:00 | 2023-02-23 11:30:00 | Andrew Salomon | SAHRA, PHRA-G |
20545 | Alterations & Additions to 81 Evans Road | Permits | On Agenda | Letter | 2023-01-24 08:41:00 | 2023-02-01 10:00:00 | Nokubonga Dlamini, Khanyi Zondi | Amafa |
20544 | PERMIT FOR RESCUE EXCAVATIONS OF SITE 37 ON PORTION 3 OF FARM OVERVLAKTE 125 MS AND VELE COAL MINE- EAST PIT EXTENSION | Permits | Final Permit Report Pending | Letter | 2023-01-24 08:17:00 | 2023-02-02 14:00:00 | Ragna Redelstorff, PhD | SAHRA |
20543 | Proposed Addition and Alterations to 14 Springfield Crescent | Permits | Closed (Approved) | Interim Comment | 2023-01-24 00:57:00 | 2023-02-01 13:00:00 | Philani Ndabezitha, Khanyi Zondi | Amafa |
20543 | Proposed Addition and Alterations to 14 Springfield Crescent | Permits | Closed (Approved) | Interim Comment | 2023-01-24 00:57:00 | 2023-02-08 10:00:00 | Philani Ndabezitha, Khanyi Zondi | Amafa |
20542 | Mukondeleli 132kV Grid Connection | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-23 21:45:00 | 2023-03-13 16:30:00 | Natasha Higgitt | SAHRA, MPHRA |
20541 | AS BUILD Additions & Alterations to 207 Adelaide Tambo Drive, Durban North | Permits | SUBMITTED | Letter | 2023-01-23 14:43:00 | 2023-02-06 12:00:00 | Sandisiwe Matole | Amafa |
20534 | Proposed Construction to Little Flower to Fairview Road | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Decision | 2023-01-20 16:01:00 | 2023-03-15 10:15:00 | Philani Ndabezitha, Khanyi Zondi | Amafa |
20527 | Second Dwelling to 39 Alamein Road, Woodlands | Permits | SUBMITTED | Letter | 2023-01-19 11:00:00 | 2023-01-26 10:45:00 | Celeste Rossouw, Khanyi Zondi | Amafa |
20524 | Proposed Klipkop-Wessels132kV Powerline, Hotazel | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-18 17:11:00 | 2023-03-17 10:00:00 | Natasha Higgitt | SAHRA, NBKB |
20524 | Proposed Klipkop-Wessels132kV Powerline, Hotazel | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Interim Comment | 2023-01-18 17:11:00 | 2023-02-15 14:30:00 | Natasha Higgitt | SAHRA, NBKB |
20523 | EIA428PR - Bondeo 140 - Lanyon Vale 376 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2023-01-18 16:26:00 | 2023-03-03 11:15:00 | Natasha Higgitt | SAHRA, NBKB |
20521 | PROPOSED RUSPOORT 2 SOLAR PV FACILITY NEAR PETRUSVILLE, DE AAR & PHILLIPSTOWN IN THE NORTHERN CAPE | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2023-01-18 15:31:00 | 2023-02-15 09:00:00 | Natasha Higgitt | SAHRA, NBKB |
20520 | PROPOSED RUSPOORT 1 SOLAR PV FACILITY NEAR PETRUSVILLE, DE AAR & PHILLIPSTOWN IN THE NORTHERN CAP | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2023-01-18 15:26:00 | 2023-02-15 08:45:00 | Natasha Higgitt | SAHRA, NBKB |
20519 | PROPOSED MIDDELPLAAS SOLAR PV FACILITY NEAR PETRUSVILLE, DE AAR & PHILLIPSTOWN IN THE NORTHERN CAPE | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2023-01-18 15:22:00 | 2023-02-15 08:45:00 | Natasha Higgitt | SAHRA, NBKB |