60 | Kathu Pan | Permits | Permit Report Approved | Final Decision | 2012-05-23 11:15:00 | 2012-06-15 12:15:00 | Ragna Redelstorff, PhD, Phillip Hine | SAHRA |
60 | Kathu Pan | Permits | Permit Report Approved | Letter | 2012-05-23 11:15:00 | 2022-10-10 12:15:00 | Ragna Redelstorff, PhD, Phillip Hine | SAHRA |
62 | Red Cap Kouga Power Line | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Letter | 2012-05-23 11:45:00 | 2012-07-13 15:00:00 | Mariagrazia Galimberti | SAHRA |
63 | Wonderwerk Cave excavation, Northern Cape | Permits | Permit Report Approved | Letter | 2012-05-23 12:00:00 | 2022-10-10 12:15:00 | Ragna Redelstorff, PhD, Phillip Hine | SAHRA |
63 | Wonderwerk Cave excavation, Northern Cape | Permits | Permit Report Approved | Letter | 2012-05-23 12:00:00 | 2012-11-29 14:30:00 | Ragna Redelstorff, PhD, Phillip Hine | SAHRA |
63 | Wonderwerk Cave excavation, Northern Cape | Permits | Permit Report Approved | Letter | 2012-05-23 12:00:00 | 2015-12-18 12:45:00 | Ragna Redelstorff, PhD, Phillip Hine | SAHRA |
252 | Healdtown Comprehensive School | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-23 15:30:00 | 2012-08-10 15:30:00 | Mariagrazia Galimberti | SAHRA, Eastern Cape |
444 | Kliparani Grain Bunker | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-24 08:35:00 | 2012-09-12 15:45:00 | Katie Smuts, Andrew Salomon | SAHRA, NWPHRA |
264 | Penhoek Pass N6 s. 4 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-24 12:45:00 | 2012-08-07 08:45:00 | Mariagrazia Galimberti | SAHRA, Eastern Cape |
283 | Whittlesea Borrow Pits, Lukhanji Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-24 14:15:00 | 2012-11-26 10:15:00 | Mariagrazia Galimberti | SAHRA |
130 | Fleet Street, East London 2 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Letter | 2012-05-28 10:15:00 | 2012-06-20 10:30:00 | Mariagrazia Galimberti | SAHRA, Eastern Cape |
960 | Belmont Valley Golf Course, Grahamstown | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-28 10:47:00 | 2012-11-29 11:00:00 | Mariagrazia Galimberti | SAHRA, ECPHRA |
113 | Fleet Street, East London | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Decision | 2012-05-28 11:00:00 | 2012-06-14 11:15:00 | Mariagrazia Galimberti | SAHRA, Eastern Cape |
172 | Erven 269 and 272 Volksrust | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-28 16:00:00 | 2012-07-13 15:00:00 | Phillip Hine, Mariagrazia Galimberti | SAHRA |
114 | Cell C telecommunication mast Dassiesfontein 86, Graaff-Reinet Rd | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Decision | 2012-05-29 12:15:00 | 2012-06-14 12:45:00 | Mariagrazia Galimberti | SAHRA, NBKB |
91 | Orlight Aggeneys Transmission Lines | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-30 14:00:00 | 2012-06-19 12:30:00 | Katie Smuts | SAHRA, NBKB |
161 | Ring Road N2 Butterworth-Dutywa | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Letter | 2012-05-30 15:00:00 | 2012-06-27 16:00:00 | Mariagrazia Galimberti | SAHRA, Eastern Cape |
259 | Umzimvubu Water Supply Scheme, Eastern Cape | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-30 16:30:00 | 2012-11-06 16:00:00 | Mariagrazia Galimberti | SAHRA, ECPHRA |
224 | Aberdeen PV | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-30 16:30:00 | 2012-07-24 09:30:00 | Mariagrazia Galimberti, Phillip Hine | SAHRA, Eastern Cape |
56 | Zuurwater 62 Boesmanland 75 MW PV | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-05-31 08:30:00 | 2012-07-04 14:30:00 | Natasha Higgitt | SAHRA, NBKB |
427 | Barolong Heritage Park | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-01 09:54:00 | 2012-09-12 14:15:00 | Katie Smuts, Phillip Hine | SAHRA, NWPHRA |
428 | Danville Park | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-01 10:06:00 | 2012-09-12 15:30:00 | Katie Smuts | SAHRA, NWPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Final Comment | 2012-06-03 11:00:00 | 2012-08-15 09:00:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Letter | 2012-06-03 11:00:00 | 2012-07-03 12:15:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Final Comment | 2012-06-03 11:00:00 | 2012-09-14 11:30:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Final Comment | 2012-06-03 11:00:00 | 2013-10-29 11:30:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Letter | 2012-06-03 11:00:00 | 2012-12-10 12:15:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Final Comment | 2012-06-03 11:00:00 | 2012-09-19 16:00:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Final Comment | 2012-06-03 11:00:00 | 2013-04-30 14:15:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
188 | Red Cap Wind Energy Facility, Kouga Municipality, Eastern Cape | Section 38 (8) - Statutory Comment Required, Permits | Studies Submitted | Final Decision | 2012-06-03 11:00:00 | 2013-09-18 11:30:00 | Mariagrazia Galimberti, Sello Mokhanya | SAHRA, ECPHRA |
61 | Zandkopsdrift 357 Prt 2 | Permits | Closed (Approved) | Final Decision | 2012-06-04 11:30:00 | 2012-06-12 14:45:00 | Mariagrazia Galimberti | SAHRA |
200 | Thombo Community Access Roads | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-04 12:30:00 | 2012-07-04 12:45:00 | Mariagrazia Galimberti, Phillip Hine | SAHRA, Eastern Cape |
96 | Tabor - Witkop 400KV Tower 167 | Section 38 (8) - Statutory Comment Required, Permits | Final Permit Report Pending | Letter | 2012-06-04 16:00:00 | 2013-01-25 14:45:00 | Mariagrazia Galimberti | SAHRA, LIHRA |
66 | Wilger PV Power Project 2647-2648 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-04 16:15:00 | 2014-07-03 10:00:00 | Katie Smuts, Phillip Hine | SAHRA, NBKB |
66 | Wilger PV Power Project 2647-2648 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-04 16:15:00 | 2012-09-17 15:45:00 | Katie Smuts, Phillip Hine | SAHRA, NBKB |
99 | Reconstruction of Pliocene palaeoshore - Northern Cape | Permits | Closed (Approved) | Letter | 2012-06-04 17:15:00 | 2012-06-18 16:30:00 | Mariagrazia Galimberti | SAHRA, Western Cape |
71 | Transnet Glosam Siding for PMG's Bishop Mine | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-06 08:15:00 | 2012-09-12 21:30:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |
73 | Proposed Housing Development on Erf 675, Kuruman | Section 38 (8) - Statutory Comment Required | Studies Pending | Interim Comment | 2012-06-06 08:30:00 | 2012-07-30 10:15:00 | Katie Smuts | SAHRA, NBKB |
72 | Boichoko Township Development, Postmasburg | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-06 08:30:00 | 2012-07-13 12:15:00 | Katie Smuts, Phillip Hine | SAHRA, NBKB |
74 | Prison Dam upgrade, Rustenburg | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Letter | 2012-06-06 08:45:00 | 2012-07-10 11:00:00 | Katie Smuts, Andrew Salomon | SAHRA, NWPHRA |
74 | Prison Dam upgrade, Rustenburg | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-06 08:45:00 | 2012-10-05 08:45:00 | Katie Smuts, Andrew Salomon | SAHRA, NWPHRA |
131 | Proposed Eskom Kentani-Seagulls 11kV Powerline, Eastern Cape | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Letter | 2012-06-06 11:30:00 | 2012-06-20 12:15:00 | Mariagrazia Galimberti | SAHRA, Eastern Cape |
79 | Khumani Housing Erven 83 & 2467 Kuruman | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-07 12:00:00 | 2012-07-11 10:45:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |
139 | Dobbin 75MW | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-07 15:00:00 | 2012-06-25 14:45:00 | Mariagrazia Galimberti, Phillip Hine | SAHRA |
80 | Voelklip Solar 557 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-07 15:45:00 | 2012-07-25 09:45:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |
80 | Voelklip Solar 557 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Decision | 2012-06-07 15:45:00 | 2012-09-03 12:00:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |
80 | Voelklip Solar 557 | Section 38 (8) - Statutory Comment Required | Closed (Approved) | Final Comment | 2012-06-07 15:45:00 | 2012-07-12 10:00:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |
85 | Garob Wind Energy 279 | Section 38 (8) - Statutory Comment Required | SUBMITTED | Interim Comment | 2012-06-08 08:30:00 | 2012-07-12 14:15:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |
85 | Garob Wind Energy 279 | Section 38 (8) - Statutory Comment Required | SUBMITTED | Final Comment | 2012-06-08 08:30:00 | 2012-10-03 15:00:00 | Katie Smuts, Mariagrazia Galimberti | SAHRA, NBKB |