Heritage Cases

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

SAHRA Application Closure

Please note the following concerning applications submitted to the South African Heritage Resources Agency (SAHRA) during the December 2023 to January 2024 period.

The full notice is available here: Notice

Special Notice

Following comments received on the proposed Revised Schedule of Fees for applications made to the South African Heritage Resources Agency (SAHRA), made in terms of Section 25(2)(l) of the National Heritage Resources Act No. 25 of 1999 (NHRA) and published in the Government Gazette of 22 July 2022, SAHRA hereby publishes the final Revised Schedule of Fees for Applications made to SAHRA. Applications for provision of services submitted to the South African Heritage Resources Authority (SAHRA), in terms of the National Heritage Resources Act, No. 25 of 1999 (NHRA) must be accompanied by a payment of the appropriate fee, taking effect from 1 January 2023

Revised Schedule of Fees for Applications made to the South African Heritage Resources Agency (SAHRA)

DEVIATION OF THE AUTHORISED 132KV POWERLINE AND ADDITION OF AN ON-SITE SUBSTATION FOR THE AUTHORISED MSENGE EMOYENI WIND ENERGY FACILITY, EASTERN CAPE PROVINCE

CaseViews

CaseHeader

Status: 

HeritageAuthority(s): 

Development Type: 

ProposalDescription: 

The authorised Msenge Emoyeni Wind Energy Facility (WEF) is located approximately 20km south of the town of Bedford in the Eastern Cape Province. The Msenge Emoyeni Wind Energy Facility has been selected as a preferred bidder via a private offtaker. In order to comply with financial close activities, the Developer has liaised with Eskom regarding the authorised 132kV powerline routing (DFFE Ref:. 12/12/20/1754/2) to the Poseidon Main Transmission Substation (“MTS”). It was determined that in order to provide suitable setbacks to the existing Amakhala and Nojoli wind farms’ turbines and to follow the existing Albany-Poseidon 132kV powerline as closely as possible, while reducing/optimizing crossing points, the authorised 132kV powerline routing would need to be deviated from the authorised routing which falls outside of the previously assessed and authorised 20-30m wide servitude. Due to the capacity at the Poseidon MTS , a 66kV powerline is intended to be constructed to take up the available capacity at the point of connection

Expanded_Motivation: 

Msenge Emoyeni Wind Farm (Pty) Ltd, proposes the following:  66kV overhead double circuit powerline approximately 22,7km long in a 300m wide assessment corridor (150m on either side), from the proposed Msenge Emoyeni WEF onsite substation to the Poseidon Main Transmission Substation (MTS)  Access tracks of up to 7m in width along the powerline route from the proposed Msenge Emoyeni WEF onsite substation to the Poseidon Main Transmission Substation (MTS).  Water course crossings along the powerline route from the proposed Msenge Emoyeni WEF onsite substation to the Poseidon Main Transmission Substation (MTS).  Development of a 33kV/132kV on-site substation with a footprint occupying an area of 250m x 200m, within a 300m radius to allow movement where possible. It must be noted that should this powerline deviation be authorised, a separate amendment process will be undertaken to remove the previously authorised 132kV powerline routing from the scope of the project. The proposed 66kV powerline route selected to evacuate power from the authorised Msenge Emoyeni WEF is informed by the most feasible grid connection point into the national grid by providing suitable setbacks to the operational Amakhala and Nojoli wind farms’ turbines and to follow the existing Albany-Poseidon 132kV powerline as closely as possible, while reducing/optimizing crossing points. The placement of the 300m grid connection corridor also provides an opportunity for the consolidation of linear electrical infrastructure within the area, inclusive of the impacts that are bundled together at this location, this can be seen as an advantage to the development of the grid connection infrastructure from a social and environmental impact perspective. Due to the deviation of the powerline infrastructure a new substation location has been selected to accommodate for the shift in powerline infrastructure.

ApplicationDate: 

Wednesday, June 22, 2022 - 13:03

CaseID: 

18863

OtherReferences: 

DepartmentApplicationTypeDeadlineDateContactPerson
21/07/2022

Heritage Reports: 

ReferenceList: 

 
 

Search form