Heritage Cases

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

SAHRA Application Closure

Please note the following concerning applications submitted to the South African Heritage Resources Agency (SAHRA) during the December 2023 to January 2024 period.

The full notice is available here: Notice

Special Notice

Following comments received on the proposed Revised Schedule of Fees for applications made to the South African Heritage Resources Agency (SAHRA), made in terms of Section 25(2)(l) of the National Heritage Resources Act No. 25 of 1999 (NHRA) and published in the Government Gazette of 22 July 2022, SAHRA hereby publishes the final Revised Schedule of Fees for Applications made to SAHRA. Applications for provision of services submitted to the South African Heritage Resources Authority (SAHRA), in terms of the National Heritage Resources Act, No. 25 of 1999 (NHRA) must be accompanied by a payment of the appropriate fee, taking effect from 1 January 2023

Revised Schedule of Fees for Applications made to the South African Heritage Resources Agency (SAHRA)

Proposed New Wolf-Skilpad-Grassridge 132KV overhead transmission line near Kariega and Kirkwood, Easter Cape Province

CaseViews

CaseHeader

Status: 

HeritageAuthority(s): 

Development Type: 

ProposalDescription: 

The proposed new 90km 132 kV transmission line will run from the Grassridge substation to Skilpad and Wolf substations alongside, as far as possible, the existing 132 kV transmission line (to be decommissioned in future).

Expanded_Motivation: 

The proposed new 132 kV transmission line will run from the Grassridge substation in a north-westerly direction to the Skilpad- and Wolf substations for approximately 46km and 44km respectively. In an effort to minimise the potential negative environmental and social impacts of the project, this transmission line is proposed to, as far as possible, run adjacent to an existing 132 kV transmission line and has an approximate length of 90km. The servitude for this new transmission line will be 31m wide. A new 3.5m wide access track will be developed within the new servitude and will run for the full length of the proposed transmission line. The servitude will be accessed via existing access tracks used for the existing 132 kV transmission line and farm roads and tracks. The proposed pylon structures will be a combination of monopole and lattice structures, depending on engineering requirements, and up to 40m high. Special structures with horizontal configuration are proposed be used where the new transmission line will need to cross other existing powerlines. Although the assessment of alternative routing options for this transmission line were initially considered by the technical team, the consideration of alternatives was ultimately to be unfeasible when comparing the potential alternative options with the preferred alternative of constructing the new transmission line adjacent to the existing 132 kV line as far as possible. As such, further costs related to preliminary designs and layouts, as well as specialist assessments of alternative options were spared, since such alternatives could not be justified when compared to the preferred alternative. Therefore, only two project alternatives have been included in this report, namely, 1) Alternative 1 (preferred): Construction of a new 132 kV transmission line adjacent to the existing 132 kV transmission line; and 2) No-Go option: The proposed project does not proceed, resulting in the existing (and failing) 132 kV line to be used for the Wolf Wind Farm. The existing 132 kV transmission line will be kept operational until such time as this new 132 kV transmission line (preferred alternative) is completed and ready for connection to the Eskom power grid.

ApplicationDate: 

Friday, April 8, 2022 - 10:34

CaseID: 

18310

OtherReferences: 

CaseReferenceDepartmentApplicationTypeDeadlineDateContactPerson
-
13/05/2022

ReferenceList: 

 
 

Search form