Heritage Cases

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

SAHRA Application Closure

Please note the following concerning applications submitted to the South African Heritage Resources Agency (SAHRA) during the December 2023 to January 2024 period.

The full notice is available here: Notice

Special Notice

Following comments received on the proposed Revised Schedule of Fees for applications made to the South African Heritage Resources Agency (SAHRA), made in terms of Section 25(2)(l) of the National Heritage Resources Act No. 25 of 1999 (NHRA) and published in the Government Gazette of 22 July 2022, SAHRA hereby publishes the final Revised Schedule of Fees for Applications made to SAHRA. Applications for provision of services submitted to the South African Heritage Resources Authority (SAHRA), in terms of the National Heritage Resources Act, No. 25 of 1999 (NHRA) must be accompanied by a payment of the appropriate fee, taking effect from 1 January 2023

Revised Schedule of Fees for Applications made to the South African Heritage Resources Agency (SAHRA)

Ruigtevallei Dreunberg Powerline

CaseViews

CaseHeader

Status: 

HeritageAuthority(s): 

Development Type: 

ProposalDescription: 

The Ruigtevallei – Dreunberg powerline is currently under construction. The powerline was subject to a Basic Assessment which received Environmental Authorisation on 29 November 2012. Three route alternatives were identified in the BA Report. eThembeni Cultural Heritage undertook a Phase 1 Heritage Impact Assessment of the three alternatives and submitted a report dated 31 October 2011 to the South African Heritage Resources Agency for review and comment. SAHRA upheld the recommendations of the report, which identified Route 3 as the preferred alternative. The Department of Environmental Affairs issued Environmental Authorisation for Route 3 to be constructed. eThembeni proposed that an archaeologist complete a walk-down of the final selected power line route option and all other activity areas prior to the start of any construction activities and assess direct impacts on discrete resources such as archaeological sites. Eskom’s preferred route in the original BA was Route 1 and they appointed Umlando to undertake the walk-down and heritage inspection. Umlando undertook this task and submitted a report to SAHRA, which was approved by the heritage authority. However, the BAR recommended Route 3, which was authorised by the DEA. Eskom nonetheless started construction on an alignment that was essentially Route 1 but with some deviations. This route is now being called Route 4 and for the purposes of this Section 24G report Route 4 is now Eskom’s preferred route. Eskom now seeks authorisation to complete construction along Route 4. eThembeni was appointed to undertake a walk-down of this route to identify any heritage resources already affected by the constructed line and that might be affected by its completion, and recommend mitigation measures. eThembeni was also tasked with assessing the other powerline route alternatives.

ApplicationDate: 

Tuesday, August 26, 2014 - 12:15

CaseID: 

6296

OtherReferences: 

ReferenceList: 

Images
 
 

Search form