FindReports

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

Advanced options
ReportRef ReportTitle ReportType ReportDatesort descending Authors AuthoringBody CommissioningCompany Post date
Heritage input optimised layout SE2602 Fronteer App S6 - Heritage input optimised layout Heritage Statement 28/04/2022 Cherene de Bruyn PGS Heritage (Pty) Ltd Savannah Environmental (Pty) Ltd 04/05/2022 - 14:47
Paleo input optimised layout SE2602 Fronteer App S7 - Paleo input optimised layout Non Impact Assessment Related Reports 28/04/2022 Elize Butler Banzai Environmental (Pty) Ltd Savannah Environmental (Pty) Ltd 04/05/2022 - 15:13
96ClarkRd-VIA-2022-04-28 Visual Impact Assessment 28/04/2022 Lindsay Napier 05/05/2022 - 08:37
96ClarkRd-VIA-2022-04-28 proposed alterations and additions at 96 Clark Road Visual Impact Assessment 28/04/2022 05/05/2022 - 09:19
Heritage Impact Assessment for the proposed expansion of the Esizayo Wind Energy Faciliity Heritage Impact Assessment: Proposed Expansion of the Esizayo Wind Energy, on Portion 2 of Farm Aanstoot 7 and Portion 1 and Remainder of Farm Leeuwenfontein 71, Western Cape (Assessment conducted under Section 38 (8) of the National Heritage Resources Act (No. 25 of 1999) as part of an Basic Assessment) HIA Phase 1 28/04/2022 John Gribble ACO Associates CC WSP Group Africa (Pty) Ltd 06/05/2022 - 11:36
JBay Gravel HERITAGE SURVEY OF THE PROPOSED JBAY GRAVEL MINE, PORTION 2 OF MENTOSKRAAL 336, HUMANSDORP, EASTERN CAPE HIA Phase 1 28/04/2022 Gavin Anderson Umlando: Archaeological Surveys & Heritage Management GCS Water and Environmental Consultants - Head Office JHB 24/06/2022 - 12:55
Kouga Sands HERITAGE SURVEY OF THE PROPOSED KOUGA SAND MINE, PORTION 8 OF KRUISFONTEIN NO. 193, HUMANSDORP, EASTERN CAPE HIA Phase 1 28/04/2022 Gavin Anderson Umlando: Archaeological Surveys & Heritage Management GCS Water and Environmental Consultants - Head Office JHB 24/06/2022 - 13:05
HIA FOR PROPOSED PROSPECTING ON PORTION ON PORTION 21 OF WAAI FONTEIN 301-ES HERITAGE AND ARCHAEOLOGICAL IMPACT ASSESSMENT FOR THE PROPOSED PROSPECTING RIGHT ON PORTION OF PORTION 21 OF THE FARM WAAI FONTEIN 301-ES, WITHIN MAGISTERITAL DISTRICT OF HARRY GWALA DISTRICT, KWAZULU NATAL PROVINCE HIA Phase 1 28/04/2022 Valerine Molo 03/05/2022 - 10:05
HIA for the Doornhoek 1 PV Facility, Klerksdorp North West HIA for the Doornhoek 1 PV Facility, Klerksdorp North West HIA Phase 1 29/04/2022 Jaco van der Walt Beyond Heritage Cape Environmental Assessment Practitioners 06/08/2022 - 11:59
HIA Desktop study for the Proposed Development of the Gidfuels Filling Station and Its Associated Infrastructures on the Farm M’phatlele 457 KS. Heritage Impact Assessment. A Desktop Study. Proposed Development of the Gidfuels Filling Station and Its Associated Infrastructures on the Farm M’phatlele 457 Ks, Portion 0 (Locatie Van Mphatlele) Heritage Impact Assessment Specialist Reports 29/04/2022 Frans Roodt Limpopo Department of Economic Development, Environmental and Tourism 29/04/2022 - 14:07
PIA for the Doornhoek 2 PV Facility North West Province PIA for the Doornhoek 2 PV Facility North West Province PIA Desktop 29/04/2022 Marion Bamford Prof Marion Bamford Cape Environmental Assessment Practitioners 06/08/2022 - 13:14
Bosveld Phosphates HIA Bosveld Phosphates HIA HIA Phase 1 29/04/2022 Dr Julius CC Pistorius 20/07/2022 - 08:47
Stilfontein Solar Energy Facilities Cluster and Associated Infrastructure, North West Province Palaeontology Specialist Study Stilfontein Solar Energy Facilities Cluster and Associated Infrastructure, North West Province Palaeontology Specialist Study PIA Phase 1 29/04/2022 Marion Bamford Prof Marion Bamford SRK Consulting (Pty) Ltd - Johannesburg 23/05/2023 - 22:11
PIA Absaland Gauteng Province PIA Absaland Gauteng Province PIA Desktop 29/04/2022 Jaco van der Walt Beyond Heritage Isquare Environmental Planning and GIS 06/08/2022 - 14:53
Ga-Rankuwa Cemetery HIA PHASE 1 HERITAGE IMPACT ASSESSMENT (HIA) FOR THE ESTABLISHMENT OF A NEW CEMETERY AND PROPOSED ACCESS ROAD, GA-RANKUWA, GAUTENG PROVINCE HIA Phase 1 30/04/2022 Leonie Marais Leonie Marais Heritage Practitioner 30/05/2022 - 14:57
23_App D4 Paleontological SSVR Palaeontological Heritage Site Sensitivity Verification Report: Proposed Khauta Solar PV Cluster and Associated Grid Connections Near Welkom, Matjhabeng Local Municipality, Free State Province Site Inspection Report 01/05/2022 John E. Almond Natura Viva CC Enviroworks 22/08/2022 - 18:29
HIA Phase 1 for Zwemkuil Gordonii_track log Amended HIA for Zwemkuil Gordonii to include the track log HIA Phase 1 01/05/2022 Lloyd Rossouw Digital Soils Africa (Pty) Ltd 12/07/2022 - 10:15
HIA Phase 1 for Zwemkuil Gordonii_track log&signed Decl Heritage Impact Assessment Phase 1 Report for Zwemkuil Gordonii that includes track log and signed declaration HIA Phase 1 01/05/2022 Lloyd Rossouw 15/08/2022 - 10:03
PHASE 1 HERITAGE IMPACT ASSESSMENT (HIA) FOR THE PROPOSED EXPANSION OF THE BOSBANK BROILER FACILITY NORTH WEST PROVINCE PHASE 1 HERITAGE IMPACT ASSESSMENT (HIA) FOR THE PROPOSED EXPANSION OF THE BOSBANK BROILER FACILITY NORTH WEST PROVINCE HIA Phase 1 01/05/2022 Leonie Marais Heritage Practitioner Leonie Marais Heritage Practitioner EnviroSynergy Consulting (Pty) Ltd 14/04/2022 - 14:20
Environmental Basic Assessment Report DRAFT BASIC ASSESSMENT REPORT ENVIRONMENTAL AUTHORISATION PROCESS FOR THE PROPOSED MIXED RESIDENTIAL DEVELOPMENT ON PORTION 149 OF THE FARM ROOIKOPPIES 297 JQ IN MARIKANA, NORTHWEST PROVINCE 02/05/2022 Edward Matenga (AHSA) Archaeological and Heritage Services Africa (Pty) Ltd (AHSA) Archaeological and Heritage Services Africa (Pty) Ltd 12/10/2022 - 10:37
HIA Camden I WEF 132kV Grid Connection Heritage Impact Assessment for the proposed Camden I Wind Grid Connection, Mpumalanga Province Heritage Impact Assessment Specialist Reports 02/05/2022 Jaco van der Walt Beyond Heritage WSP Group Africa (Pty) Ltd 11/05/2023 - 14:01
HIA Camden I SEF 132kV Grid Connection Heritage Impact Assessment for the proposed Camden I Wind Grid Connection, Mpumalanga Province Heritage Impact Assessment Specialist Reports 02/05/2022 Jaco van der Walt Beyond Heritage WSP Group Africa (Pty) Ltd 11/05/2023 - 14:09
HIA Camden I WEF 132kV Grid Connection Heritage Impact Assessment for the proposed Camden I Wind Grid Connection, Mpumalanga Province Heritage Impact Assessment Specialist Reports 02/05/2022 Jaco van der Walt Beyond Heritage WSP Group Africa (Pty) Ltd 11/05/2023 - 14:34
Phase 1 Cultural Heritage Impact Assessment: Phase 1 Cultural Heritage Impact Assessment: THE PROSPECTING RIGHT APPLICATION INCLUDING ASSOCIATED INFRASTRUCTURE, STRUCTURE AND EARTHWORKS OF ERNA FRANCINE ERASMUS TO PROSPECT FOR DIAMOND ALLUVIAL (DA) ON THE FARM AANSLUIT 250 (EXCLUDING A CERTAIN AREA), REGISTRATION DIVISION:HOPETOWN, NORTHERN CAPE PROVINCE HIA Phase 1 03/05/2022 Johnny van Schalkwyk 03/05/2022 - 14:55
Palaeo LoE: Tharisa Waste Rock Dumps Palaeontological Letter of Exemption: Proposed Tharisa Waste Rock Dumps near Marikana Palaeontological Specialist Reports 03/05/2022 marion Bamford 29/11/2022 - 16:41
D2312 culvert washaway project D2312 culvert washaway project, Ndwedwe Local Municipality, KwaZulu-Natal Heritage Statement 03/05/2022 Jean Beater JLB Consulting EnviroPro 15/07/2022 - 10:32
Archaeology Report: Poortjie Wes SEF ARCHAEOLOGICAL SPECIALIST STUDY In terms of Section 38(8) of the NHRA for a Proposed development of the Poortjie Renewable Energy Facility Solar PV Projects near Beaufort West in the Western Cape AIA Phase 1 03/05/2022 Nicholas Wiltshire, Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 14/06/2022 - 09:21
Palaeontology Report: Poortjie Wes SEF PALAEONTOLOGICAL HERITAGE: COMBINED FIELD-BASED & DESKTOP STUDY Six Solar PV Projects within the Poortjie Renewable Energy Facility near Nelspoort, Beaufort West Local Municipality, Central Karoo District, Western Cape PIA Phase 1 03/05/2022 John Almond Natura Viva CC Savannah Environmental (Pty) Ltd 14/06/2022 - 09:21
HIA: Brakpan PV 1 HERITAGE IMPACT ASSESSMENT In terms of Section 38(8) of the NHRA for the Proposed development of the Brakpan PV 1 (Option A) as part of the Poortjie Renewable Energy Facility Solar PV Projects near Beaufort West in the Western Cape HIA Phase 1 03/05/2022 Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 14/06/2022 - 09:30
24_App D5 Heritage & Archaeological SSVR Heritage & Archaeological Verification Report, Proposed Khauta Solar PV Cluster Near Welkom, Matjhabeng Local Municipality, Free State Province Site Inspection Report 04/05/2022 Jonathan Kaplan Agency for Cultural Resources Management Enviroworks 22/08/2022 - 18:48
Esizayo WEF Specialist Statement ESIZAYO WIND ENERGY FACILITY EA AMENDMENT: SPECIALIST IMPACT STATEMENT Heritage Statement 05/05/2022 John Gribble ACO Associates CC WSP Group Africa (Pty) Ltd 03/06/2022 - 09:05
Heritage Exemption Letter - Thaba Filling Station MOTIVATION FOR EXEMPTION FROM FULL PHASE 1 HERITAGE IMPACT ASSESSMENT – PROPOSED THABA ECO VILLAGE LIFESTYLE ESTATE FILLING STATION DEVELOPMENT ON THE REMAINDER OF PORTION 2 OF THE FARM RIETVLEI 101IR, CITY OF JOHANNESBURG, GAUTENG HIA Letter of Exemption 05/05/2022 APELSER ARCHAEOLOGICAL CONSULTING 08/12/2022 - 13:55
DWARSLOOP TOWNSHIP ESTABLISHMENT PROPOSED TOSNHIP ESTABLISHMENT IN DWARSLOOP WITIHIN BUSHBUCK RIDGE LOCAL MUNICIPALITY IN MPUMALANGA Heritage Impact Assessment Specialist Reports 06/05/2022 Leonie Marais-Botes GKM Consulting PTY LTD Bushbuckridge Local Municipality 06/05/2022 - 13:10
MIDRAND LICENSING PROPOSED OFFICE BLOCK PROPOSED CONSTRUCTION OF AN OFFICE BLOCK ON KAALFONTEIN FARM NO 23IR PORTION 6 IN MIDRAND WITHIN THE CITY OF JOHANNESBURG HIA Letter of Exemption 06/05/2022 Leonie Marais-Botes Gauteng - Department of Agriculture and Rural Development GKM Consulting PTY LTD 06/05/2022 - 13:21
RAMOSUKULA SCHOOL UPGRADE PROPOSED UPGRADING OF RAMOSUKULA SECONDARY SCHOOL Heritage Impact Assessment Specialist Reports 06/05/2022 Francois Coetzee GKM Consulting PTY LTD Gauteng - Department of Agriculture and Rural Development 06/05/2022 - 13:34
COLIGNY TOWNSHIP DEVELOPMENT PROPOSED TOWNSHIP DEVELOPMENT ON ERVEN 563, 564 AND 698 IN COLIGNY WITHIN THE NORTHWEST PROVINCE Heritage Impact Assessment Specialist Reports 06/05/2022 Leonie Marais-Botes GKM Consulting PTY LTD Department of Economic Development, Tourism & Environmental Affairs 06/05/2022 - 12:15
FORMALISATION OF LETHLABILE INFORMAL SETTLEMENT Notice of an application for environmental authorisation and heritage permit for the proposed formalisation of portion twenty-three of the Nietgedacht farm no 242JQ in the Northwest Province Heritage Impact Assessment Specialist Reports 06/05/2022 Leonie Marais-Botes Mpumalanga - Department of Agriculture, Rural Development, Land and Environmental Affairs GKM Consulting PTY LTD 06/05/2022 - 12:49
Esizayo WEF - Palaeontological Statement PALAEONTOLOGICAL HERITAGE COMMENT: PART 2 AMENDMENT FOR THE AUTHORIZED ESIZAYO WIND ENERGY FACILITY NEAR LAINGSBURG, CENTRAL KAROO DISTRICT MUNICIPALITY, WESTERN CAPE & KAROO HOOGLAND DISTRICT MUNICIPALITY, NORTHERN CAPE Palaeontological Specialist Reports 07/05/2022 John Almond Natura Viva CC WSP Group Africa (Pty) Ltd 03/06/2022 - 09:07
Heritage Screener: Orkney PV OHL DESKTOP HERITAGE SCREENING ASSESSMENT FOR THE PROPOSED ORKNEY SOLAR PV OVERHEAD POWER LINE AND SWITCHING STATION, NORTH WEST PROVINCE HIA Letter of Exemption 09/05/2022 Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 17/05/2022 - 13:06
PHASE 1 ARCHAEOLOGICAL AND HERITAGE IMPACT ASSESSMENT REPOR PHASE 1 ARCHAEOLOGICAL AND HERITAGE IMPACT ASSESSMENT REPORT FOR THE PROPOSED LIQUEFIED PETROLEUM GAS (LPG) STORAGE FACILITY ON ERF 79 MARELDEN EXTENSION 5 TOWNSHIP WITHIN EMALAHLENI LOCAL MUNICIPALITY, MPUMALANGA PROVINCE AIA Phase 1 09/05/2022 Trust Mlilo 18/06/2022 - 13:33
Seuwe Bridge HIA Phase 1 Cultural Heritage Impact Assessment: THE PROPOSED CONSTRUCTION OF A ROAD BRIDGE, REFERRED TO AS SEUWE BRIDGE, IN THE GREATER TUBATSE LOCAL MUNICIPALITY, LIMPOPO PROVINCE HIA Phase 1 10/05/2022 Johnny van Schalkwyk J A van Schalkwyk 04/10/2022 - 13:38
HIA: Merino WEF HERITAGE IMPACT ASSESSMENT In terms of Section 38(8) of the NHRA for the Proposed Merino Wind Farm which forms part of the Great Karoo Wind Energy Facility development near Richmond in the Northern Cape HIA Phase 1 10/05/2022 Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 17/05/2022 - 12:28
Heritage Screener: SCSC solar PV Desktop Heritage Screening Assessment for the Proposed development of SCSC solar PV and battery storage facility near Northam in the Limpopo and North West Provinces Heritage Scoping 10/05/2022 Darya Presnyakova, Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 03/06/2022 - 16:33
RECTIFICATION APPLICATION: SHARON LODGE PORTION 75 RECTIFICATION APPLICATION: SHARON LODGE PORTION 75 HIA Phase 1 10/05/2022 Leonie Marais Botes Leonie Marais Botes EnviroSynergy Consulting (Pty) Ltd 24/07/2023 - 11:27
Heritage Screener: SBPM Solar PV Desktop Heritage Screening Assessment for the Proposed development of SBPM solar PV and battery storage facility near Northam in the Limpopo and North West Provinces Heritage Scoping 10/05/2022 Darya Presnyakova, Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 03/06/2022 - 16:37
HIA: Great Karoo PV Facilities HERITAGE IMPACT ASSESSMENT In terms of Section 38(8) of the NHRA for the Proposed Nku, Moriri and Kwana PV Facilities which form part of the Great Karoo Renewable Energy Facility development near Richmond in the Northern Cape HIA Phase 1 10/05/2022 Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 17/05/2022 - 12:48
PALAEONTOLOGICAL DESKTOP ASSESSMENT PALAEONTOLOGICAL DESKTOP ASSESSMENT for THE PROSPECTING RIGHT APPLICATION FOR DIAMONDS ALLUVIAL ON THE FARM AANSLUIT 250, REGISTRATION DIVISION: HOPETOWN, NORTHERN CAPE PROVINCE PIA Desktop 11/05/2022 Elize Butler Banzai Environmental (Pty) Ltd 03/05/2022 - 14:54
Heritage Impact Assessment Report Heritage Impact Assessment for the Proposed upgrade of infrastructure at Gilead Substation located within Mogalakwena Local Municipality, in the Limpopo Province Heritage Impact Assessment Specialist Reports 12/05/2022 Roy Muroyi 14/06/2022 - 10:55
Exemption Letter Request - Sishen Iron Ore Mine Solar PV Facility Application for exemption from a Heritage Impact Assessment for the Proposed Development of a Solar PV Facility and Associated Infrastructure at the Sishen Iron Ore Mine HIA Letter of Exemption 12/05/2022 Jaco van der Walt Beyond Heritage SLR Consulting (South Africa) (Pty) Ltd 12/09/2022 - 11:24
Eskom Gilead Heritage Report Heritage Impact Assessment Report for the proposed upgrade of infrastructure at Gilead substation located within Mogalakwena Local Municipality, in the Limpopo Province Heritage Impact Assessment Specialist Reports 12/05/2022 Roy Muroyi Tsimba Archaeological Footprints (Pty) Ltd Myezo Environmental Management Services (Pty) Ltd 24/08/2022 - 16:01