Changes to SAHRIS!
The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:
- A new & modernised look and layout
- Improved site usage flows with respect to applications and content creation
- Improved site performance and stability
Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.
The new site can be found here:
SAHRIS | SAHRIS
Displaying 17801 - 17850 of 18975
ReportRef | ReportTitle | ReportType | ReportDate | Authors | AuthoringBody | CommissioningCompany | MapID < 2009 | Post date |
---|---|---|---|---|---|---|---|---|
ARCHAEOLOGICAL AND CULTURAL HERITAGE ASSESSMENT SPECIALIST STUDY | ARCHAEOLOGICAL AND CULTURAL HERITAGE ASSESSMENT SPECIALIST STUDY | Heritage Impact Assessment Specialist Reports | 22/07/2022 | Eric Ndivhuho Mathoho | Vhufa Hashu Heritage Consultancy CC | Vhufa Hashu Heritage Consultancy CC | 04/11/2022 - 14:13 | |
Impala SPP HIA | Impala Solar Power Plant Heritage Impact Assessment | Heritage Impact Assessment Specialist Reports | Johnny van Schalkwyk | 02/06/2021 - 12:41 | ||||
Heritage Impact Assessment - Sol Invictus 1 | Heritage Impact Assessment for the Proposed Sol Invictus 1 PV Facility, Namakwaland Magisterial District, Northern Cape Province | Heritage Impact Assessment Specialist Reports | 08/04/2016 | Jayson Orton | ASHA Consulting(Pty) Ltd | Savannah Environmental (Pty) Ltd | 22/04/2016 - 14:54 | |
HIA: MBB Dairy, Mooi Rover, KZN | CULTURAL HERITAGE IMPACT ASSESSMENT OF THE PROPOSED EXPANSION OF THE BAYONNE DAIRY, ON PORTIONS 10 (OF 7) 11 (of 8), 12 (of 9), 13 (of 2), 15 (of 14) AND REMAINDER OF PORTION 3 (OF 2) OF FARM RIPLEY NO. 2211, AND PORTION 16 of FARM NIEKERKS FONTEIN NO. 1031, MOOI RIVER, MPOFANA MUNICIPALITY, KWAZULU-NATAL | Heritage Impact Assessment Specialist Reports | 01/06/2013 | Frans Prins | Active Heritage CC | Green Door Environmental | 15/10/2013 - 09:05 | |
The Whiskin | THE PROPOSED WHISKIN HOUSING ESTATE, CROWTHORN AGRICULTURAL HOLDINGS, MIDRAND REGION, GAUTENG PROVINCE | Heritage Impact Assessment Specialist Reports | 01/02/2015 | Johnny Van Schalkwyk | JA van Schalkwyk Heritage Consultant | LEAP - Lanscape Architect Environmental Planner | 18/01/2016 - 17:49 | |
HIA for Modikwa Platinum Mine (MPM) | Heritage Impact Assessment for Modikwa Platinum Mine, Doornbosch 521501. | Heritage Impact Assessment Specialist Reports | 21/02/2018 | Lysette Rothmann-Guest | Archaetnos Culture & Cultural Resource Consultants | SRK Consulting (Pty) Ltd - Johannesburg | 27/11/2019 - 15:59 | |
HIA, borrow pit extension (DR02242/0.3/R/100) on portion 1 of Dassen Klip A 169 near Porterville | Heritage Impact Assessment: MR 02242 Piketberg Porterville - West Coast District Municipality, Western Cape | Heritage Impact Assessment Specialist Reports | 27/03/2013 | Vidamemoria Heritage Consultants | Nadeson Consulting Services | CTS_503683 | 17/04/2018 - 18:48 | |
BRMO - New Railway Bridge Heritage Report | A REPORT ON A HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED NEW RAILWAY BRIDGE AT THE BLACK ROCK MINING OPERATIONS, CLOSE TO HOTAZEL, NORTHERN CAPE PROVINCE. | Heritage Impact Assessment Specialist Reports | 01/03/2019 | Anton van Vollenhoven | Archaetnos Culture & Cultural Resource Consultants | Assmang Black Rock Mining Operations | 30/05/2019 - 11:59 | |
DEPLOYMENT OF A FIBRE NETWORK WITHIN THE SOL PLAATJE MUNICIPAL AREA REDUCED SCALE | DEPLOYMENT OF A FIBRE NETWORK WITHIN THE SOL PLAATJE MUNICIPAL AREA REDUCED SCALE (JULY 2021) REV 1 | Heritage Impact Assessment Specialist Reports | 22/07/2021 | christine havenga | Frogfoot Networks | 18/07/2021 - 19:59 | ||
Kalkaar 132kV Power Line Heritage Impact Assessment | PROPOSED POWER LINES AND ASSOCAITED INFRASTRUCTURE FOR THE PROPOSED KALKAAR SOLAR THERMAL POWER PROJECT NEAR KIMBERLEY, FREE STATE PROVINCE | Heritage Impact Assessment Specialist Reports | 20/05/2016 | Wouter Fourie | PGS Heritage and Grave Relocation Consultants | PGS Heritage and Grave Relocation Consultants | 14/06/2016 - 14:18 | |
Preliminary Skeletal Analysis Report | Preliminary Human Remains Assessment: Proposed Kusile Invest 133 Giyani Gold Mine Project on the Demarcated Portions of State Land of Greater Giyani 891 LT, Giyani, Limpopo | Heritage Impact Assessment Specialist Reports | 04/10/2021 | Hester Roodt | 30/01/2022 - 15:11 | |||
De Rust South HIA | Heritage Impact assessment for the Proposed De Rust South WEF | Heritage Impact Assessment Specialist Reports | 01/04/2023 | Jaco van der Walt | Beyond Heritage | Enviro-Insight CC | 09/06/2023 - 10:30 | |
Riverside Cemetery HIA | Riverside Cemetery Heritage Impact Assessment | Heritage Impact Assessment Specialist Reports | 01/01/2014 | Jean Beater | Active Heritage CC | Enviroedge | 16/04/2015 - 14:42 | |
Rondekop Heritage Impact Assessment Report | ENVIRONMENTAL IMPACT ASSESSMENT (EIA) FOR THE PROPOSED 325MW RONDEKOP WIND ENERGY FACILITY BETWEEN MATJIESFONTEIN SUTHERLAND IN THE NORTHERN CAPE PROVINCE Heritage Impact Assessment | Heritage Impact Assessment Specialist Reports | 10/09/2018 | IIan Smeyatsky | PGS Heritage (Pty) Ltd | SiVEST SA (Pty) Ltd | 09/05/2019 - 16:42 | |
Heritage Report - Steynrus Solar Energy Facility | Archaeological Impact Assessment Report for the Proposed Steynsrus (19.5MW) Photovoltaic Plant, Free State Province | Heritage Impact Assessment Specialist Reports | 06/06/2013 | Jaco van der Walt | Heritage Contracts and Archaeological Consulting | Savannah Environmental (Pty) Ltd | 30/08/2013 - 10:18 | |
Fairy Wing Trading PRA | A DESKTOP HERITAGE IMPACT ASSESSMENT REPORT FOR THE FAIRY WING TRADING PROSPECTING RIGHTS APPLICATION ON VARIOUS FARM AND FARM PORTIONS IN THE MAGISTERIAL DISTRICT OF ZULULAND UPHONGOLO LOCAL MUNICIPALITY, KZN - APAC022/54 | Heritage Impact Assessment Specialist Reports | 01/06/2022 | Anton Pelser | APELSER ARCHAELOGICAL CONSULTING | Licebo Environmental and Mining (Pty) Ltd | 09/11/2022 - 17:00 | |
Vryburg Solar 1 Heritage Report | Gultural Heritage Impact Assessment for the Proposed Development of a 100 MW (115(MW DC) Solar Photovoltaic Facility (Vryburg Solar 1) and Associated 132kv Transmission Line near Vryburg, North West Province. | Heritage Impact Assessment Specialist Reports | 03/08/2018 | J.A. van Schalkwyk | J van Schalkwyk | 16/08/2018 - 14:55 | ||
Vygenhoek HIA | Heritage Impact Assessment Specialist Reports | Jaco van der Walt | Department of Mineral Resources - Mpumalanga | 07/06/2021 - 12:29 | ||||
Proposed CIA Amendment Process, Richards Bay | HERITAGE SURVEY OF THE PROPOSED RICHARDS BAY CENTRAL INDUSTRIAL AREA | Heritage Impact Assessment Specialist Reports | Gavin Anderson | Umlando: Archaeological Surveys & Heritage Management | Coastal & Environmental Services - Grahamstown | 10/05/2017 - 13:01 | ||
Rietfontein Mixed-Use Development | THE PROPOSED RAPID LAND RELEASE PROGRAMME FOR THE GAUTENG DEPARTMENT OF HUMAN SETTLEMENT: RIETFONTEIN SITE | Heritage Impact Assessment Specialist Reports | 14/02/2020 | Cherene de Bruyn | PGS Heritage (Pty) Ltd | Department of Human Settlements (Provincial - Gauteng) | 07/12/2020 - 17:04 | |
IXI3002_HIA | Heritage Impact Assessment Report: Environmental Authorisation for the Proposed Imvula Coal Mine | Heritage Impact Assessment Specialist Reports | 29/02/2016 | Justin du Piesanie, Johan Nel | Digby Wells Environmental | Ixia Coal (Pty) Ltd | 30/03/2016 - 09:32 | |
HIA FOR THE CONSTRUCTION OF A PEDESTRIAN PATHWAY AND CYCLE PATH IN THE MABOPANE AREA OF GAUTENG PROVINCE | CULTURAL HERITAGE RESOURCES IMPACT ASSESSMENT FOR THE CONSTRUCTION OF A PROPOSED PEDESTRIAN PATHWAY AND CYCLE PATH AT MABOPANE GAUTENG PROVINCE | Heritage Impact Assessment Specialist Reports | 22/05/2013 | Udo Kusel | African Heritage Consultants CC | SPOOR Environmental Services (PTY) Ltd. | 20/09/2013 - 15:59 | |
Heritage Impact Assessment Ikageng Extension 13 | Cultural heritage assessment for the PROPOSED IKAGENG EXTENSION 13 ON PORTION 2 OF THE REMAINDER OF TOWN AND TOWNLANDS OF POTCHEFSTROOM 435IQ, NORTH WEST PROVINCE | Heritage Impact Assessment Specialist Reports | 01/05/2015 | Johnny Van Schalkwyk | 13/10/2015 - 11:59 | |||
COP6679 - NID | Notification of Intent to Develop - Environmental Authorisation Process for the Expansion of the Copper Sunset Mining Right Area | Heritage Impact Assessment Specialist Reports | 02/03/2021 | Shannon Hardwick, Justin du Piesanie | Digby Wells Environmental | Copper Sunset Sand (Pty) Ltd | 02/03/2021 - 19:49 | |
Desktop Heritage Impact Assessment Report | Blue Lounge Trading 107 (Pty) Ltd: Prospecting Activities, Desktop Heritage Impact Assessment Report, September 2019 | Heritage Impact Assessment Specialist Reports | 06/09/2019 | Stephan Gaigher | G&A Heritage Management Consultants | 20/07/2021 - 15:33 | ||
Rooipunt Solar Thermal Power Park Power Line, Northern Cape | POWERLINES FOR PROPOSED ROOIPUNT SOLAR THERMAL POWER PARK PROJECT NEAR UPINGTON, ZF MGCAWU DISTRICT MUNICIPALITY, NORTHERN CAPE PROVINCE Heritage Impact Assessment | Heritage Impact Assessment Specialist Reports | 22/05/2016 | Wouter Fourie | PGS Heritage and Grave Relocation Consultants | Sivest - Gauteng | 22/06/2016 - 08:08 | |
Madlanzini DBAR Heritage Report | Cultural Heritage Impact Assessment Of The Proposed Iswepe (Madlanzi/Ermelo), Coal-Link Project, Including Substation And Powerline Alternatives, Mpumalanga Province. | Heritage Impact Assessment Specialist Reports | 23/01/2014 | Frans Prins, Sidney Miller | Sivest - Gauteng | 21/04/2015 - 16:17 | ||
Cultural heritage impact assessment | Cultural heritage impact assessment for THE DEVELOPMENT OF THE PROPOSED KAGISO SOLAR POWER PLANT ON THE REMAINING EXTENT OF THE FARM KAMEELAAR NO 315 REGISTRATION DIVISION KURUMAN, NORTHERN CAPE PROVINCE | Heritage Impact Assessment Specialist Reports | 01/03/2016 | Johnny Van Schalkwyk | 30/05/2016 - 11:35 | |||
Coleskop Heritage Impact Assessment | Heritage Impact Assessment Specialist Reports | Umlando: Archaeological Surveys & Heritage Management | 20/08/2019 - 09:08 | |||||
Lebone Solar Farm - HIA | Phase 1 Archaeological Impact Assessment & Palaeontological Assessment Lebone Solar Farm The Remaining Extent of the Farm Onverwag No. 728 and Portion 2 of the Farm Vaalkranz Np. 220, Welkom, Free State Province | Heritage Impact Assessment Specialist Reports | 17/10/2013 | Karen Van Ryneveld, Gideon Groenewald | ArchaeoMaps Archaeological Consultancy | Enviroworks | 12/11/2013 - 15:08 | |
Heritage Impact Assessment Report (Jan'22) | Solaris Fields App I - HIA | Heritage Impact Assessment Specialist Reports | 11/01/2022 | Cherene de Bruyn | PGS Heritage (Pty) Ltd | Savannah Environmental (Pty) Ltd | 12/01/2022 - 12:59 | |
Updated Ithemba Grid Heritage Impact Assessment Report 2 | Ithemba Wind Energy Facility (WEF) – 132kV Grid connection and substation Heritage Impact Report | Heritage Impact Assessment Specialist Reports | 20/02/2018 | Wouter Fourie | PGS Heritage (Pty) Ltd | Sivest - Gauteng | 23/03/2018 - 12:00 | |
Exemption from HIA for EPL TD2 remining | Application for exemption from a Heritage Impact Assessment for the Retreatment of Eastern Platinum (Pty) Ltd (EPL) Tailings Dam 2, Marikana, North West Province | Heritage Impact Assessment Specialist Reports | 08/08/2023 | Jaco van der Walt | Beyond Heritage | Alta van Dyk Environmental Consultants cc | 12/10/2023 - 10:56 | |
HIA: ISDUDANA CAUSEWAY | HERITAGE IMPACT ASSESSMENT OF THE PROPOSED ISDUDANA CAUSEWAY, NONGOMA MUNICIPALITY NORTHERN KWAZULU-NATAL | Heritage Impact Assessment Specialist Reports | 14/02/2014 | Frans Prins | Active Heritage CC | Green Door Environmental | 17/02/2014 - 12:31 | |
HIA Hoekplaas | Heritage Impact Assessment for Multiple Proposed Solar Energy Facilities on Farm Hoekplaas 146, Copperton, Northern Cape. | Heritage Impact Assessment Specialist Reports | 09/07/2013 | Jayson Orton | ACO Associates CC | Aurecon - Cape Town | 24/03/2015 - 10:51 | |
HERITAGE IMPACT ASSESSMENT FOR DRYCUT HOUSING PROJECT | HERITAGE IMPACT ASSESSMENT FOR THE DRYCUT HOUSING PROJECT, MADADENI AMAJUBA DISTRICT | Heritage Impact Assessment Specialist Reports | 08/12/2019 | Gavin Anderson | Umlando: Archaeological Surveys & Heritage Management | Bizycon Pty Ltd | 01/07/2020 - 22:17 | |
Karkloof Dairy, KZN | CULTURAL HERITAGE IMPACT ASSESSMENT OF THE PROPOSED ESTABLISHMENT OF A 1000 HEAD DAIRY ON SUB 28 OF THE FARM WELGEVONDEN NO. 969, KARKLOOF, KWAZULU-NATAL | Heritage Impact Assessment Specialist Reports | 18/08/2013 | Frans Prins | Active Heritage CC | Green Door Environmental | 25/10/2013 - 11:35 | |
RESIDENTIAL DEVELOPMENT AT KURUMAN | FIRST PHASE ARCHAEOLOGICAL & HERITAGE INVESTIGATION OF THE PROPOSED 222 ERVEN RESIDENTIAL DEVELOPMENT AT 27HA ERF 1, KURUMAN, NORTHERN CAPE PROVINCE | Heritage Impact Assessment Specialist Reports | 25/11/2014 | Cobus Dreyer | YB Mashalaba & Associates Consultants | YB Mashalaba & Associates Consultants | 09/08/2015 - 20:47 | |
HIA & PIA Impact Assessment for the Waaihoek Grid Infrastructure | HERITAGE IMPACT ASSESSMENT In terms of Section 38(8) of the NHRA for the PROPOSED DEVIATION TO THE APPROVED WAAIHOEK GRID CONNECTION, UTRECHT, KZN | Heritage Impact Assessment Specialist Reports | 15/07/2022 | Jenna Lavin | Cedar Tower Services | 11/08/2022 - 07:06 | ||
2020/JvS/051Wouter | THE MINING RIGHT APPLICATION FOR DIAMONDS ON PORTION OF REMAINING EXTENT OF PORTION 9 (WOUTER) OF THE FARM LANYON VALE 376, NEAR NIEKERSHOOP, PIXLEY KA SEME DISTRICT MUNICIPALITY, NORTHERN CAPE PROVINCE. | Heritage Impact Assessment Specialist Reports | 01/07/2020 | Johnny van Schalkwyk | 18/03/2021 - 09:09 | |||
Final 2013 May DEA HIA | Heritage Impact Assessment Report And Heritage Management Plan For The Venetia Underground Project And Consolidation Of Existing Operations For De Beers Consolidated Mines Limited -Venetia Mine | Heritage Impact Assessment Specialist Reports | 04/03/2015 | Siyathembana Trading 293 Pty Ltd. | De Beers Consolidated Mines (Pty) Ltd | 04/03/2015 - 09:53 | ||
Updated Graskoppies Grid Heritage Impact Assessment Report | Graskoppies Wind Energy Facility (WEF) – 132kV Grid connection and substation: Heritage Impact Report | Heritage Impact Assessment Specialist Reports | 20/02/2018 | Wouter Fourie | PGS Heritage (Pty) Ltd | Sivest - Gauteng | 27/02/2018 - 09:53 | |
Palaeontological Pre-Construction Walkthrough Report for Sutherland and Rietrug | AUTHORISED 140MW RIETRUG (DFFE Ref: 12/12/20/1782/1/AM5) AND 140MW SUTHERLAND (DFFE Ref: 12/12/20/1782/2/AM6) WIND ENERGY FACILTIES (WEFS) AND THEIR ASSOCIATED GRID CONNECTIONS (DFFE REF: 14/12/16/3/3/1/2457/AM1, 14/12/16/3/3/1/2458 & 14/12/16/3/3/1/2077/AM2) BETWEEN SUTHERLAND & MERWEVILLE, KAROO HOOGLAND MUNICIPALITY (NAMAQUA DISTRICT), NORTHERN CAPE AND LAINGSBURG MUNICIPALITY (CENTRAL KAROO DISTRICT), WESTERN CAPE PROVINCES | Heritage Impact Assessment Specialist Reports | 01/12/2022 | John E Almond | Natura Viva CC | Natura Viva CC | 15/12/2022 - 11:19 | |
Eskom Rhombus Lethabong powerline and Substation Heritage Assessment | Cultural heritage assessment for the PROPOSED RHOMBUS 88KV DISTRIBUTION POWER LINE AND SUBSTATION, WEST OF BRITS, NORTH WEST PROVINCE | Heritage Impact Assessment Specialist Reports | 30/04/2014 | Johnny Van Schalkwyk | Envirolution Consulting (Pty) Ltd | 08/07/2014 - 11:07 | ||
HIA for the Proposed Subsidized Housing at Cornfields. | PHASE ONE CULTURAL HERITAGE IMPACT ASSESSMENT OF A PROPOSED LOW INCOME HOUSING DEVELOPMENT AT CORNFIELDS D NEAR ESTCOURT, KWAZULU-NATAL. | Heritage Impact Assessment Specialist Reports | 01/10/2014 | Frans Prins, Sian Hall | Active Heritage CC | 15/10/2014 - 15:45 | ||
Heritage Impact Assessment (Nov'21) | Appendix I - Heritage Impact Assessment | Heritage Impact Assessment Specialist Reports | 11/11/2021 | Cherene de Bruyn | PGS Heritage (Pty) Ltd | Savannah Environmental (Pty) Ltd | 12/11/2021 - 08:23 | |
HIA Burnlea Trust Wetland Rehab | CULTURAL HERITAGE IMPACT ASSESSMENT OF THE PROPOSED ESTABLISHMENT OF AN 800 COW DAIRY, THREE NEW DAMS, EXPANSION OF AN EXISTING DAM AND THE CULTIVATION OF 131 HA OF VELD ON PORTION 3 AND PORTION 4 OF NEW BIGGIN NO 13390, PORTION 1 OF LOT FP 364 NO 11628, REM OF LOT FP 277B NO. 9266, REM OF LOT FP 320 NO 8965, REM OF SUNRISE NO 5567 AND REM OF BURNLEA NO 15994 LOCATED NEAR TO UNDERBERG | Heritage Impact Assessment Specialist Reports | 10/07/2011 | Frans Prins | Active Heritage CC | Green Door Environmental | 14/07/2017 - 11:12 | |
HIA of access roads for Zeerust PV Plant | Phase 1 Heritage Impact Assessment of the Proposed Access roads for the Zeerust PV Plant. | Heritage Impact Assessment Specialist Reports | Anton Pelser | APELSER ARCHAEOLOGICAL CONSULTING | RE CAPITAL 2 (Pty) Ltd | 31/08/2020 - 12:02 | ||
HIA Aggeneys Grid 1 | HERITAGE IMPACT ASSESSMENT: PROPOSED GRID CONNECTION INSFRASTRUCTURE FOR AGGENEYS 1 SOLAR PHOTOVOLTAIC FACILITY, NAMAKWALAND MAGISTERIAL DISTRICT, NORTHERN CAPE | Heritage Impact Assessment Specialist Reports | 31/03/2019 | Jayson Orton | ASHA Consulting(Pty) Ltd | Savannah Environmental (Pty) Ltd | 16/05/2019 - 11:20 | |