Heritage Cases

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

SAHRA Application Closure

Please note the following concerning applications submitted to the South African Heritage Resources Agency (SAHRA) during the December 2023 to January 2024 period.

The full notice is available here: Notice

Special Notice

Following comments received on the proposed Revised Schedule of Fees for applications made to the South African Heritage Resources Agency (SAHRA), made in terms of Section 25(2)(l) of the National Heritage Resources Act No. 25 of 1999 (NHRA) and published in the Government Gazette of 22 July 2022, SAHRA hereby publishes the final Revised Schedule of Fees for Applications made to SAHRA. Applications for provision of services submitted to the South African Heritage Resources Authority (SAHRA), in terms of the National Heritage Resources Act, No. 25 of 1999 (NHRA) must be accompanied by a payment of the appropriate fee, taking effect from 1 January 2023

Revised Schedule of Fees for Applications made to the South African Heritage Resources Agency (SAHRA)

RE Capital 3A Solar Development

CaseViews

CaseHeader

Status: 

HeritageAuthority(s): 

Development Type: 

ProposalDescription: 

The establishment of a 75 Megawatt Photo Voltaic Solar Facility on 166ha of Remainder of the Farm Dyason’s Klip 454 for RE Capital 3 (Pty) Ltd.

Expanded_Motivation: 

The RE Capital 3 Solar Development (id 3324) was approved by SAHRA in a letter dated 19 March 2014 (Ref: 9/2/032/0004). As discussed between SAHRA and the applicant and SAHRA and the EAP, three new cases will be uploaded to SAHRIS in order to meet the requirements of the Department of Energy for the bidding process as follows: 1. The original approval needs to be split into 3 seperate entities (the previous approval allowed for a 225MW project on 500ha in 3 phases - this requested change merely allows for a seperate approval letter for each of the phases). 2. The farm portion needs to be ammended to reflect the correct farm portion as per the deeds office (The previous approval authorises the facility on portion 12 of Dyasonsklip 454 as per the surveyor general registration - The deeds office however lists the property as the Remainder of the farm 454 (although this is the exact same portion of land)) 3. The previous approval letter was made out to the EAP, Cape EAPrac and it is requested that this be made out to the applicant for each of the phases.

ApplicationDate: 

Monday, May 26, 2014 - 11:29

CaseID: 

5713

OtherReferences: 

ReferenceList: 

Citation
Morris, D. July 2013. RE Capital 3 Solar Development on the property Dyasons Klip west of Upington, Northern Cape: Scoping phase Heritage Morris, D. February 2014. Capital 3 Solar Development on the property Dyasons Klip west of Upington, Northern Cape: Archaeological Impact Assessment – proposed ‘central’ development footprint Almond, J. March 2014. PALAEONTOLOGICAL HERITAGE BASIC ASSESSMENT: DESKTOP STUDY Proposed RE Capital 3 Solar Development on the property Dyason’s Klip near Upington , Northern Cape
 
 