FindReports

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

Advanced options
ReportRef ReportTitle ReportType ReportDate Authors AuthoringBody CommissioningCompany Post date
HIA-BlackwoodPowerline Proposed Blackwood Solar Energy Facility on Portion 1 of Pandamsfontein 1593, South East of Kimblery, in the Tokologo Local Municipality, Free State: Heritage Impact Assessment Report Heritage Impact Assessment Specialist Reports 25/08/2014 David Morris McGregor Museum Savannah Environmental (Pty) Ltd 24/03/2015 - 10:48
Esizayo Powerline Paleontological Report PROPOSED 400 KV POWERLINE CONNECTION FOR THE ESIZAYO WIND ENERGY FACILITY NEAR LAINGSBURG, CENTRAL KAROO DISTRICT MUNICIPALITY, WESTERN CAPE: PALAEONTOLOGICAL HERITAGE BASIC ASSESSMENT PIA Phase 1 20/12/2016 John E Almond Natura Viva CC WSP Environmental Pty Ltd - Johannesburg 04/08/2017 - 10:14
HIA for MAhlathini Road CULTURAL HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED UPGRADING OF MAHLATHINI ROAD Heritage Impact Assessment Specialist Reports 06/05/2016 Frans Prins 09/05/2016 - 12:37
Phase 1 HIA (Including Palaeontological Assessment) for Paul Seun Thukgwi Phase 1 Heritage Impact Assessment (including Palaeotological Assessment) for Paul Seun Thukgwi for the proposed mine prospecting on the Remaining Extent of Portion 1 of the farm Viegulands Put 42, Prieska District, Northern Cape Province. HIA Phase 1 24/08/2017 Edward Matenga 30/10/2017 - 04:57
Palaeontological Impact Assessment: Phase 1 Field Study The Proposed Establishment of the Monument Park X15 Township on a Certain Part of the Remainder of Portion 27 of the Farm Waterkloof. City of Tshwane Metropolitan Municipality, Gauteng Province Farm: A Certain Part of the Remainder of Portion 27 of the Farm Waterkloof 378-JR HIA Phase 1 01/10/2018 Heidi Fourie Dr Heidi Fourie J Paul van Wyk 07/11/2018 - 16:16
Archaeological and Palaeontological Archaeological and Palaeontological Impact Assessment FOR THE UPDATED EMP OF THE TRANS HEX MINING OPERATIONS, RICHTERSVELD, NORTHERN CAPE Archaeological Specialist Reports 02/12/2010 Jaco van der Walt Heritage Contracts and Archaeological Consulting Myezo Environmental Management Services 10/02/2022 - 13:32
PIA Waterloo Palaeontological Heritage Assessment: Combined Desktop & Field-based Study Proposed PV Solar Facility on a portion of the farm Waterloo 992 near Vryburg, Naldi Local Municipality, North West Province 07/01/2013 John Almond Natura Viva CC DPS79 Solar Energy (Pty) Ltd. 21/07/2016 - 16:04
HERITAGE IMPACT ASSESSMENT: PROPOSED 400 MW PHOTOVOLTAIC FACILITY AND POWER LINE ON OLYVEN KOLK 187/3 & 187/7, KENHARDT MAGISTERIAL DISTRICT, NORTHERN CAPE HERITAGE IMPACT ASSESSMENT: PROPOSED 400 MW PHOTOVOLTAIC FACILITY AND POWER LINE ON OLYVEN KOLK 187/3 & 187/7, KENHARDT MAGISTERIAL DISTRICT, NORTHERN CAPE Required under Section 38(8) of the National Heritage Resources Act (No. 25 of 1999). SAHRA Case No.: 11248 1st draft: 02 October 2018 HIA Phase 1 02/10/2018 Jayson Orton ASHA Consulting(Pty) Ltd Wine Estate Capital Management (Pty) Ltd 19/02/2019 - 15:26
Brakfontein HIA HERITAGE IMPACT ASSESSMENT FOR BRAKFONTEIN THERMAL COAL MINE HIA Phase 1 17/08/2012 Natasha Higgitt Digby Wells Environmental Universal Coal (Pty) Ltd 29/08/2012 - 12:56
HIA 1st Phase Heritage Impact Assessment :THE PROPOSED RONDEBULT OUTFALL SEWER LINE. HIA Phase 1 Sidney Miller 20/04/2022 - 15:36
Annual Report (1 Nov 2000 - 31 Oct 2001) - Collecting of Fossils. Permit No. 80/00/12/003/60 (Valid Until - 1 February 2004) Annual Report (1 Nov 2000 - 31 Oct 2001) - Collecting of Fossils. Permit No. 80/00/12/003/60 (Valid Until - 1 February 2004) Archaeological Permit Report 12/11/2001 Billy De Klerk 16/06/2012 - 08:54
SACO Mining (PTY) Ltd- NC 12522 PR BASIC ASSESSMENT REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME REPORT FOR THE APPLICATION OF A PROSPECTING RIGHT SITUATED ON THE REMAINING EXTENT OF THE FARM RIETFONTEIN 250, IN THE MAGISTERIAL DISTRICT OF NAMAQUALAND 12/10/2020 - 14:30
HIA: Aggeneys PV Solar Energy Facility HERITAGE IMPACT ASSESSMENT: PROPOSED AGGENEYS PHOTOVOLTAIC SOLAR ENERGY FACILITY AT BLOEMHOEK NEAR AGGENEYS, NORTHERN CAPE PROVINCE HIA Phase 1 01/04/2013 David Morris Solar Capital Aggeneys 10/02/2014 - 10:37
HIA Project 7: Sparrow PV Heritage Impact Assessment Project 7: Sparrow PV Stilfontein North West Province Jaco van der Walt Beyond Heritage SRK Consulting (Pty) Ltd - Western Cape 17/04/2023 - 11:28
PIA Desktop Study - Eldorado Park Proper Project C - Erf 4793 Eldorado Park Proper Project C Housing Development - Erf 4793, City of Johannesburg Metropolitan Municipality, Gauteng Province Palaeontological Impact Assessment: Desktop Assessment PIA Desktop 06/11/2020 Heidi Fourie Dr Heidi Fourie K2M Environmental 30/11/2020 - 13:56
Phase 1 Eskom Pienaarsriver CNC HIA Study A Phase 1 Heritage Impact Assessment Study for Eskom's Proposed CNC in Pienaarsrivier in the Limpopo Province HIA Phase 1 20/09/2013 Julius CC Pistorius Texture Environmental Consultants 30/03/2014 - 17:52
Phase 1 Cultural Heritage Resources Impact Assessment Phase 1 Cultural Heritage Resources Impact Assessment for the expansion of the existing cemetery site on the remainder of portion 3 of the farm Sjambok Zijn Oude Kraal 258 JR Ga-Rankuwa Tshwane Gauteng HIA Phase 1 22/04/2015 Udo Kusel African Heritage Consultants CC Aurecon - Head Office 17/06/2015 - 09:46
Heritage Screener: Merino WEF (Great Karoo) Desktop Heritage Screening Assessment for the Proposed Merino Wind Farm which forms part of the Great Karoo Wind Energy Facility development near Richmond in the Northern Cape Heritage Scoping 01/09/2021 Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 15/11/2021 - 17:04
Desktop Archaeological and Cultural Heritage Study - Proposed Rezoning, Subdivision and Development, Portion 6 of Farm 743, East London, BCMM, Eastern Cape Desktop Archaeological and Cultural Heritage Study - Proposed Rezoning, Subdivision and Development, Portion 6 of Farm 743, East London, BCMM, Eastern Cape AIA Desktop 18/03/2020 Karen Van Ryneveld Imithi Services 18/03/2020 - 16:04
Palaeontological Report - Boundary Solar Facility Phase 1 Palaeontological Impact Assessment of the Boundary PV Solar Facility on Farm Karreeboom 1716, Boshof Distric, FS Province PIA Phase 1 31/01/2014 Lloyd Rossouw Palaeo Field Services Savannah Environmental (Pty) Ltd 10/09/2013 - 09:15
Constantia Kloof Stormwater Phase 2 HIA HIA Report for the Constantia Kloof Storm water phase2 HIA Phase 2 30/03/2021 Siegwalt Udo Kusel African Heritage Consultants CC African Heritage Consultants CC 30/06/2021 - 11:40
Heritage Pre-Construction Walkthrough PRE-CONSTRUCTION ARCHAEOLOGICAL SURVEY OF THE AUTHORISED 140MW RIETRUG WIND ENERGY FACILITY AND ASSOCIATED GRID CONNECTION INFRASTRUCTURE, NORTHERN & WESTERN CAPE PROVINCES Heritage Impact Assessment Specialist Reports 01/12/2022 Jayson Orton ASHA Consulting(Pty) Ltd ASHA Consulting(Pty) Ltd 08/12/2022 - 17:10
AIA ON PORTIONS FOR THE PROPOSED NEW HOPE PEDESTRIAN WALKWAY PROJECT, BUFFALO CITY MUNICIPALITY, EASTERN CAPE PROVINCE ARCHAEOLOGICAL IMPACT ASSESSMENT (AIA) ON PORTIONS OF FARM 1038 FOR THE PROPOSED NEW HOPE PEDESTRIAN WALKWAY PROJECT, BUFFALO CITY MUNICIPALITY, EASTERN CAPE PROVINCE AIA Phase 1 02/07/2020 Neels Kruger Exigo3 Sustainability ControLab South Africa (Pty) Ltd 05/08/2020 - 15:04
Manjekwini HIA Phase 1 Heritage Impact Assessment for the proposed construction of Emanjokweni Community Hall in Manjokweni, Inkosi Langalibalele Local Municipality, Kwa-Zulu Natal Roy Muroyi Tsimba Archaeological Footprints (Pty) Ltd Tlhaho Environmental Consultants (Pty) Ltd 20/09/2023 - 16:03
TRP New TSF Desktop Palaentological Study TRP New TSF Desktop Palaentological Study PIA Desktop 23/07/2013 Bruce Rubidge University of the Witwatersrand GCS Water and Environmental Consultants - Head Office JHB 12/11/2013 - 14:30
Rising Star Empire Cave 2014 Annual Report Report on the Scientific Activities at the Empire Cave/Rising Star Cave System 2014 Palaeontological Permit Report 24/01/2015 Lee R. Berger 24/01/2015 - 14:11
PDA proposed Mogalakwena Solar Pv Project Limpopo Palaeontological Desktop Assessment For The Proposed Mogalakwena Solar Pv Project In Limpopo, South Africa PIA Desktop 15/06/2021 Elize Butler Banzai Environmental (Pty) Ltd 19/08/2021 - 11:00
HIA Klipgats Pan Heritage Impact Assessment for Multiple Proposed Solar Energy Facilities on the Remainder of Farm Klipgats Pan 117, Copperton, Northern Cape Heritage Impact Assessment Specialist Reports 15/07/2013 Jayson Orton ACO Associates CC Aurecon - Cape Town 24/03/2015 - 11:47
Stiebel Place HIA 2017 HIA: Development at 5 Stiebel Place, Westville, KwaZulu-Natal, May 2017 HIA Phase 2 31/05/2017 Lindsay Napier Lindsay Napier Architect Elphick Proome Architects 08/08/2017 - 11:32
HIU Report-Shaepeville Massacre Memorial Site Site Inspection Report-Sharpeville Massacre Memorial Site 07/03/2016 10/05/2016 - 11:23
Rust De Winter HIA HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED ROOIKOP MINING PERMIT APPLICATION, GAUTENG PROVINCE HIA Phase 1 26/07/2017 Jaco van der Walt Heritage Contracts and Archaeological Consulting Greenmined Environmental 31/10/2017 - 10:57
Heritage Impact Assessment for Messina Diamonds (Pty) Ltd PHASE I HERITAGE IMPACT ASSESSMENT (INCLUDING PALAEONTOLOGICAL ASSESSMENT) REQUESTED IN TERMS OF SECTION 38 OF THE NATIONAL HERITAGE RESOURCES ACT NO 25/1999 FOR THE PROPOSED MINE PROSPECTING AND APPLICATION FOR MINING RIGHTS ON THE FARM 85, BARKLY WEST DISTRICT, NORTHERN CAPE PROVINCE HIA Phase 1 08/12/2018 Edward Matenga Archaeological and Heritage Services Africa (Pty) Ltd 08/11/2018 - 13:09
AMANYUSWA HIA DESKTOP LETTER OF EXEMPTION FOR THE AMANYUSWA RURAL HOUSING PROJECT HIA Phase 1 15/02/2022 Gavin Anderson Umlando: Archaeological Surveys & Heritage Management K2M Environmental 15/02/2022 - 20:56
Quaggasfontein LoE Exemption of a Phase 1 Heritage Impact Assessment for a proposed new 400 m - long water pipeline connection for an existing pivot on the farm Quaggasfontein 98, Colesberg, NC Province. Heritage Study 21/07/2016 National Museum Bloemfontein 22/07/2016 - 10:26
RECOMMENDED EXEMPTION FROM FURTHER PALAEONTOLOGICAL STUDIES RECOMMENDED EXEMPTION FROM FURTHER PALAEONTOLOGICAL STUDIES: PROPOSED 300 MW PHOTOVOLTAIC ELECTRICITY GENERATION FACILITY & ASSOCIATED 132 kV POWER LINE ON PORTIONS 6 AND 3 OF FARM 187 OLYVENKOLK, KENHARDT DISTRICT, NORTHERN CAPE John E. Almond PhD (Cantab.) Natura Viva cc, PO Box 12410 Mill Street, Cape Town 8010, RSA naturaviva@universe.co.za September 2018 PIA Desktop 01/09/2018 John E. Almond Natura Viva CC Solar Energy Land (Pty) Ltd 19/02/2019 - 16:21
HIA Slanghuevel Prospecting ARCHAEOLOGICAL AND HISTORICAL INVESTIGATION OF THE PROPOSED DIAMOND MINING ACTIVITIES AT PORTION 5 (SNYDERS RUSH) OF THE FARM SLANG HEUVEL 160, BARKLY WEST DISTRICT, NORTHERN CAPE HIA Phase 1 09/07/2012 Cobus Dreyer Heritage Archaeologist & Consultant Rock Runner Consultants 05/09/2012 - 09:34
HIA MTHOMBOWESIZWE HERITAGE IMPACT ASSESSMENT HIA Phase 1 21/04/2022 21/04/2022 - 09:22
Icarus SPP - PIA 15/02/2023 - 07:55
Archaeological Potential of Groenrivier Mond and Island Point (3017DC) : Report No. 1 Archaeological Potential of Groenrivier Mond and Island Point (3017DC) : Report No. 1 AIA Phase 1 01/01/1993 Graham Avery Iziko: South African Museum 16/06/2012 - 08:54
PIA Amendment letter - Badenhorst PV2 PIA Amendment letter - Badenhorst PV2 Heritage Statement 13/10/2020 John Almond Natura Viva CC 14/10/2020 - 14:37
Finsch Mine Updated Report Updated report on the Cultural Heritage Impact Assessment for Petra Diamonds Finsch Mine Archaeological Monitoring 08/01/2014 Lloyd Rossouw National Museum Bloemfontein Petra Diamonds (Pty) Ltd 12/02/2014 - 11:43
Phase 1 Archaeological Impact Assessment for the Prospecting Right Application in Northern Cape Province PHASE 1 HIA FOR HIA/ARCHAEOLOGICAL IMPACT ASSESSMENT FOR PROSPECTING RIGHT APPLICATION FOR THE PURPOSE OF PROSPECTING MANGANESE ORE ON PORTION 2 OF THE FARM EAST 270 SITUATED IN THE MAGISTERIAL DISTRICT OF JOHN TAOLO GAETSEWE (KURUMAN) IN NORTHERN CAPE PROVINCE. HIA Phase 1 30/03/2023 Trust Mlilo 17/04/2023 - 16:37
Bloemsmond 2 BESS Heritage Statement Bloemsmond 2 BESS Heritage Statement Heritage Statement 01/09/2020 Jaco van der Walt Heritage Contracts and Archaeological Consulting Cape Environmental Assessment Practitioners 01/12/2020 - 12:51
Bellevue / Hillcove report HERITAGE SURVEY FOR THE PROPOSED HILLCOVE HOUSING DEVELOPMENT, PIETERMARITZBURG HIA Phase 1 27/09/2011 Gavin Anderson, Deborah Whelan Umlando: Archaeological Surveys & Heritage Management Laurusco Developments (Pty) Ltd 31/03/2014 - 14:38
Phase 1 Heritage Impact Assessment for Makukukwe 522, Thaba Letsele 643 and Plaas 503 Phase 1 Heritage Impact Assessment study for Makukukwe 522, Thaba Letsele 643 and Plaas 503. HIA Phase 1 15/06/2015 Edward Matenga Manngwe Mining 17/06/2015 - 12:20
AIA For the proposed Midridge Park Ext. 25 Township Development, Midrand, Gauteng Archaeological Impact Assessment For the proposed Midridge Park Ext. 25 Township Development, Midrand, Gauteng AIA Phase 1 16/04/2015 Jaco van der Walt Heritage Contracts and Archaeological Consulting Prism Environmental Management Services cc 15/07/2015 - 11:45
Cultural Heritage Assessment - Prime Spot Cultural Heritage Assessment of a Portion of Portion 1 of the Farm Vischgat 467IR, Sedibeng District Municipality, Midvaal Local Municipality, Gauteng Heritage Impact Assessment Specialist Reports 01/09/2013 Francois P Coetzee Umhlaba Environmental Consulting CC 18/01/2018 - 16:50
CTS16_048 Savannah Substation & Power Line NC and Updated Addendum Olifantshoek Substation & Power Line with Updated Addendum 23/05/2017 Kyla Bluff, Jenna Lavin CTS Heritage Savannah Environmental (Pty) Ltd 19/09/2016 - 10:41
Khumani Heritage Impact Assessment HERITAGE IMPACT ASSESSMENT FOR KHUMANI IRON ORE MINE NEW WATER RETURN DAM, PIPELINES AND WATER CONTAINMENT FACILITY, SISHEN, NORTHERN CAPE Heritage Impact Assessment Specialist Reports 30/04/2019 Jaco van der Walt Heritage Contracts and Archaeological Consulting Envirogistics (Pty) Ltd 15/05/2019 - 18:10
HIA: Grootgeluk Mine HERITAGE SURVEY REPORT OF THE KUMBA PROPERTIES AT GROOTGELUK MINE, LEPHALALE AREA, LIMPOPO PROVINCE HIA Phase 1 Johnny Van Schalkwyk National Cultural History Museum 22/01/2013 - 09:33