Heritage Cases

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

SAHRA Application Closure

Please note the following concerning applications submitted to the South African Heritage Resources Agency (SAHRA) during the December 2023 to January 2024 period.

The full notice is available here: Notice

Special Notice

Following comments received on the proposed Revised Schedule of Fees for applications made to the South African Heritage Resources Agency (SAHRA), made in terms of Section 25(2)(l) of the National Heritage Resources Act No. 25 of 1999 (NHRA) and published in the Government Gazette of 22 July 2022, SAHRA hereby publishes the final Revised Schedule of Fees for Applications made to SAHRA. Applications for provision of services submitted to the South African Heritage Resources Authority (SAHRA), in terms of the National Heritage Resources Act, No. 25 of 1999 (NHRA) must be accompanied by a payment of the appropriate fee, taking effect from 1 January 2023

Revised Schedule of Fees for Applications made to the South African Heritage Resources Agency (SAHRA)

Permit application for the Destruction/Demolition of the existing revetment on erf 2487 at 516 Beach Street, Port Nolloth,

CaseViews

CaseHeader

Status: 

HeritageAuthority(s): 

Case Type: 

Development Type: 

ProposalDescription: 

The project scope entails the destruction and removal of existing revetment along the shoreline which will be replaced with new revetment material. The revetment area designated for destruction has an approximate surface area of 1600 square meters. Based on the archaeological study conducted on site, suitable mitigating factors have been implemented to prevent the sites impact on objects of possible heritage significance. The site is located in the Northern Cape.

Expanded_Motivation: 

The revetment area will be cleared to a certain extent to make it more accessible for earth moving machines. The initial clearing will be done by front end loader and/or backactor and possibly be assisted by some dump trucks. Placement of temporary works to protect works during construction. Material removed from the present revetment may temporarily be stockpiled close by or removed to an approved spoil site. Access for construction vehicles (earthmoving machines, dump trucks etc.) to the revetment site will be from the south end of the revetment – i.e. starting in the vicinity of the existing slipway. The concrete fragments and building rubble may either be spoiled off-site or crushed for re-use in the new revetment – i.e. recycled. Having achieved initial clearing and tidying up of the revetment site, reconstruction can commence. Certain construction activities will be restricted to low tide conditions only. Geotextiles may be required if the migration of sand is to be controlled. The new revetment will include a surface lining consisting of rubble/rock. Some of this rubble will be sourced from the stock pile mentioned earlier. Additional rock, probably two or three sizes of fragments, will be imported from a commercial quarry. A fleet of dump trucks will transport rock from the quarry to the site. This material will, ideally, be tipped directly onto the revetment site, starting with the smallest size fragments. Material will be spread and levelled by front end loader or backactor. This process will be repeated for the next size of fragment until the final layer of rubble has been completed. The complete site (revetment, adjacent road and car park, Contractor’s lay down area) will be cleared, re-instated and rehabilitated before the contractor departs. Cognisance will be taken of the findings in the site archaeological report during construction activities.

ApplicationDate: 

Tuesday, March 7, 2017 - 11:30

CaseID: 

10776

OtherReferences: 

CaseReference
10609

ReferenceList: 

Images
 
 

Search form