Permits

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

Centaur Pre-disturbance Survey Permit renewal

HeritageAuthority: 

PermitID: 

224

PermitHolder: 

PermitTo: 

PermitDate: 

Monday, April 1, 2013 to Monday, March 31, 2014

NHRA: 

Activities: 

Conditions: 

Conditions:

1. If the permit holder is not present on the site at all times then the heritage authority must be provided with the names and qualifications of the authorised representatives.
2. Adequate recording methods as specified in the Regulations and Guidelines pertaining to the National Heritage Resources Act must be employed. The positions of all datum points from the wreck must be marked on an accurate plan of the site, which must also include a title, date, north arrow and scale.
3. Work must be limited to the exploration (pre-disturbance survey) in order to determine the identity, condition and extent of the site, “Centaur”. This permit does not allow for excavation or the removal of material from the wreck site.
4. This permit gives the holder the sole right to work on the site for the duration of the permit period.
5. A detailed log book must be kept to record daily progress, the mapping and location of finds, features of the wreck and sea and weather conditions.
6. A report on the results of the pre-disturbance survey must be submitted to the heritage authority issuing this permit on or before the 31 March 2014. Reprints of all published papers or copies of theses and/or reports resulting from this work must be lodged with the heritage authority.
7. If satisfactory progress reports are not received, this permit may be cancelled. If a published report has not appeared within three years of the lapsing of this permit, the report required in terms of the permit will be made available to researchers on request.
8. It is the responsibility of the permit holder to protect the site during and after work has been completed on site to the satisfaction of the heritage authority.
9. It is the responsibility of the permit holder to obtain permission from the landowner for each visit, and conditions of access imposed by the landowner must be observed.
10. The heritage authority shall not be liable for any losses, damages or injuries to persons or properties as a result of any activities in connection with this permit.
11. The heritage authority reserves the right to cancel this permit by notice to the permit holder.

PermitFeePaidDate: 

19/03/2013