Permits

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

Excavation at Penhill, Kirkwood District, amendment of permit holder

HeritageAuthority: 

PermitID: 

1759

PermitDate: 

Monday, May 12, 2014 to Monday, December 1, 2014

NHRA: 

Activities: 

SiteReference: 

Conditions: 

This permit is an amendment of permit 80/11/10/001/51 issued by SAHRA on the 8th of November 2011. Dr Ryan Gibbon is added as permit holder to the permit with Dr Kathleen Kuman and Mr Marc Lotter. All previous conditions stipulated in the original permit apply.

Conditions:

 1. If the permit holders are not to be present on the site at all times then SAHRA must be provided with the names and qualifications of the authorised representatives.
2. Adequate recording methods as specified in the Regulations and Guidelines pertaining to the National Heritage Resources Act must be used. Note that the position of all excavations must be marked on a plan of each site.
3. A standard site record form must be lodged with the Albany Museum.
4. All material collected and excavated, as well as field notes and records, will be curated by the Albany Museum.
5. A progress report must be submitted to SAHRA on or before 1 December 2012 and 01 December 2013 and a final report is due on or before 01 December 2014. SAHRA reserves the right to withhold further permits if progress is not deemed satisfactory.
6. Reprints of all published papers, or copies of theses or reports resulting from this work must be lodged with SAHRA.
7. If a published report has not appeared within three years of the lapsing of this permit, the report required in terms of the permit will be made available to researchers on request.
8. It is the responsibility of the permit holders to obtain permission from the landowner for each visit, and conditions of access imposed by the landowner must be observed.
9. It is the responsibility of the permit holders to fill in excavations and protect sites during and after excavation to the satisfaction of SAHRA and the landowner.
10. SAHRA shall not be liable for any losses, damages or injuries to persons or properties as a result of any activities in connection with this permit.
11. SAHRA reserves the right to cancel this permit by notice to the permit holders.

PDF of Permit: 

AttachmentSize
PDF icon Penhill amendment_permit.pdf135.26 KB
 
 