Permits

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

9/2/036/0002

HeritageAuthority: 

PermitID: 

3626

PermitDate: 

Monday, July 11, 2022 to Friday, July 11, 2025

NHRA: 

Conditions: 

This permit is issued to Applicant: Bakopane Architects: Paul Johannes Labuschagne for consent for the construction and alterations to the existing Miners Compound into a functional Museum for Palaeontological and Archaeological finds within the Taung Skull World Heritage Site Precinct.

1. If Bakopane Architects: Paul Johannes Labuschagne is not to be present on the site at all times then
SAHRA must be provided with the names and qualifications of the authorized representatives.
2. The activities will consist of: • All relevant excavations and preparation of the site for construction • Removal
and disposal of all waste material related to construction • The building of the structure and making good
according to documentation
3. All waste material and leftover equipment will be removed from the site once the construction has been
completed, and the site will be left in the manner it was found (save for the new action).
4. The landowner must be consulted before any intervention and (permit holder) or a representative of the
the landowner should be on site on the first day of the action).
5. It is understood that Bakopane Architects: Paul Johannes Labuschagne will photograph the affected area
prior to the construction and again after the construction has been completed and submitted to SAHRA as
built drawings highlighting any revisions.
6. A final report on the results of the activities in the form of a closing report should be submitted to SAHRA by
no later than 30 days after the final completion of works by a contractor on site.
7. It is the responsibility of the permit holder to obtain permission from the landowner for each visit, and to
ensuring that she has an understanding with the landowner concerning: the number of visitors and workers; speed limits on access roads; possible prohibitions on off-road driving; size, type and number of vehicles permitted; possible prohibitions on trespassing beyond the site; disturbing fauna, flora or substrate; appropriate hours of visiting and working on the site; use of firewood, electricity and water; lighting fires and the prevention of uncontrolled fires and any fencing necessary to protect livestock. Conditions of access imposed by the landowner must be observed.
8. SAHRA shall not be liable for any losses, damages or injuries to persons or properties as a result of any activities in connection with this permit. 
9. SAHRA reserves the right to cancel this permit by notice to the permit holder.
10. This permit is subject to a general appeal and may be suspended should an appeal against the decisions be received by SAHRA within 14 days from the date of the permit. SAHRA may not be held responsible for any costs or losses incurred in the event of the suspension or retraction of this permit.
 
 



PermitFeePaidDate: 

11/07/2022
 
 