CaseNo:
PermitID:
4054
PermitHolder:
PermitTo:
PermitDate:
Monday, May 29, 2023 to Friday, May 29, 2026
NHRA:
KZNHA:
Activities:
SiteReference:
Conditions:
- The plan of the test pits must be provided before excavation commences;
- The destruction of the site must be pre-approved following the submission of the Phase II report;
- The report must include a full investigation into the relationship of the subject site to the previously identified sites and provide conclusive evidence as to whether this site is one of the previously identified sites or whether it is a new site.
- Excavated archeological material becomes the property of the KZN Amafa and Research Institute. Collection and removal of material from the site for further research or for retention in a private collection requires a permit through the submission of a Form E application;
PermitFeePaidDate:
29/05/2023
PDF of Permit:
Attachment | Size |
---|---|
![]() | 121.59 KB |