5827 |
PROPOSED DECOMMISSIONING OF THE OLD SLUDGE DRYING AREA AT THE GOUDKOPPIES WASTE WATER TREATMENT PLANT |
10/06/2014 |
Closed (Approved) |
16497 |
Application for the proposed Nzalo 2x 88kV Powerline. |
19/05/2021 |
Pending & Under Assessment |
5831 |
Borutho-Witkop 400kV Transmission Line |
11/06/2014 |
Pending & Under Assessment |
14937 |
Environmental Authorisation (EA) Amendment Application for Vryheid Traction Station and the Associated Turnin Power Lines, Kwazulu-Natal |
25/02/2020 |
DRAFT |
15222 |
Eskom's Grootvlei MES Suspension Application and AEL Variation Request |
06/07/2020 |
Closed (Approved) |
12585 |
Exarro Sublime Road Upgrades |
13/06/2018 |
For Noting |
12006 |
Kudu Integration 400kV powerline amendment |
29/11/2017 |
Closed (Approved) |
5830 |
Medupi-Borutho 400kV Transmission Line |
11/06/2014 |
Pending & Under Assessment |
8856 |
Northern Alignment 765kV Power Lines, Free State, Northern and Western Cape Provinces |
07/12/2015 |
Closed (Approved) |
14938 |
Phase 1 HIA Report for Vryheid Substation and Associated 2 X 88kV Power Lines |
25/02/2020 |
DRAFT |
11686 |
Proposed Aggeneis-Paulputs 400kV Powerline and Substation Upgrades |
18/09/2017 |
Closed (Approved) |
12207 |
PROPOSED DEVELOPMENT OF APPROXIMATELY 170KM 1X400kV MAPHUTHA-WITKOP POWERLINE |
09/02/2018 |
DRAFT |
9286 |
Proposed East Water Cooling Tower Treatment |
18/03/2016 |
Closed (Approved) |
8448 |
PROPOSED ISUNDU 765/400 KV SUB-STATION AND TURN-IN TRANSMISSION LINES, KZN MIDLANDS. |
19/09/2015 |
Closed (Approved) |
17470 |
THE PROPOSED ESKOM AZAADVILLE 4KM 400kV DEVIATION POWER LINE |
04/11/2021 |
SUBMITTED |
16498 |
Vryheid 2x 88kV Turn-In Power Lines |
19/05/2021 |
Closed (Approved) |